Unlock stock picks and a broker-level newsfeed that powers Wall Street.

Westwater Resources Announces 2024 Business and Financial Updates

In This Article:

100% of Anticipated Annual Phase I CSPG Production Under Contract

10% Reduction in Estimated Construction Costs of Kellyton Graphite Plant

CENTENNIAL, Colo., March 21, 2025--(BUSINESS WIRE)--Westwater Resources, Inc. (NYSE American: WWR), an energy technology and battery-grade natural graphite development company ("Westwater" or the "Company"), is pleased to announce its results for the year ended December 31, 2024, and to provide business and financial updates.

2024 Key Highlights

During 2024, Westwater achieved critical milestones and achievements related to its planned natural graphite business, notably:

  • On February 5, 2024, Westwater announced its off-take agreement with SK On for Coated Spherical Purified Graphite ("CSPG").

  • On July 18, 2024, Westwater announced its offtake agreement for CSPG with Fiat Chrysler Automobiles ("FCA").

  • With these Offtake Agreements in place, the Company has committed to sell 100% of its anticipated Phase I production capacity and partially committed a portion of the anticipated Phase II production capacity from its Kellyton Graphite Plant.

  • During 2024, Westwater continued to evaluate its plant design, construction schedule and related costs, resulting in a decrease of $26 million in the estimated capital cost of Phase I. The revised estimate of $245 million includes an 11% contingency and 2% escalation factor on the remaining uncommitted spend.

  • As of December 31, 2024, Westwater has completed construction of its qualification line at the Kellyton Graphite Plant to purify and coat larger bulk samples of CSPG for customer evaluations. The qualification line is designed to produce approximately 1 metric tonne per day of CSPG and the samples produced on it will be representative of CSPG mass production at the plant.

  • During 2024, Westwater continued Phase I construction at the Kellyton Graphite Plant deploying approximately $123 million in capital expenditures since inception of the project.

  • Westwater received investment committee approval from the lead lender (a global financial institution), and the Company now is working with its investment banker, Cantor Fitzgerald, to finalize the overall syndication and closing of the $150 million debt financing to complete Phase I construction of the Kellyton Graphite Plant.

"Recent policy decisions by the federal government have created uncertainty in the capital markets, which has negatively impacted the timing and increased the number of lenders needed to complete the syndication of the debt financing to complete Phase I construction of the Kellyton Graphite Plant," said Terence J. Cryan, Westwater’s Executive Chairman. "However, while the debt financing is taking longer than we originally estimated, the fundamentals of our business remain solid and customer engagement is active."