Torex Gold Provides Q4 2024 Update on Media Luna Project

In This Article:

Construction substantially complete and first copper concentrate on track for March

(All amounts expressed in U.S. dollars unless otherwise stated)

Toronto, Ontario--(Newsfile Corp. - February 4, 2025) - Torex Gold Resources Inc. (the "Company" or "Torex") (TSX: TXG) provides a Q4 2024 update on the development of its Media Luna Project ("Media Luna"). Unless otherwise stated, progress and milestones referenced in this press release are as of December 31, 2024.

Jody Kuzenko, President & CEO of Torex, stated:

"The Media Luna Project is now in its final months, sitting at 94% complete as of the end of 2024. We are well on track to complete the project and produce first copper concentrate by the end of Q1 2025, with engineering concluded, procurement substantially complete, underground development tracking well ahead of schedule, and surface construction advancing per plan.

"The tie-ins at the processing plant are on track to commence towards the end of February, with all major deliveries required to support the tie-in period now on site. In Q4, teams were able to take advantage of a planned maintenance period at the process plant and conducted initial synchronization and testing of the variable frequency drives for the ball mill, which we expect will streamline and de-risk the installation process and support efficient commissioning in March.

"Average monthly underground lateral development rates remained ahead of budget at 1,300 meters per month. Definition drilling is also well ahead of plan, with drilling for 2024 stopes completed ahead of schedule, most of the stopes planned to be mined in 2025 drilled off, and drilling for 2026 underway. Our target is to have a minimum of one year of stope inventory on hand going forward. With an excellent head start on both definition drilling and underground development, which will further accelerate in 2025, we now expect to achieve the designed mining rate of 7,500 tonnes per day by mid-2026, six months ahead of the schedule set out in the Technical Report.

"In terms of project capital, Q1 2025 is expected to be the last quarter of material investment in Media Luna and, with commercial production expected in early Q2 2025, we are well-positioned to pivot back to positive free cash flow generation by mid-year. The robust free cash flow anticipated from Morelos places Torex in a solid position to quickly repay the modest level of debt taken on to fund Media Luna, begin returning capital to shareholders, and support increased investment in our plans for continued growth at Morelos and beyond."