Torex Announces Q1 2016 Results and Updated Life of Mine Plan

TORONTO, ONTARIO--(Marketwired - May 12, 2016) -

(All amounts expressed in U.S. Dollars unless otherwise stated)

Torex Gold Resources Inc. (the "Company" or "Torex") (TXG.TO) announced today its financial results for the three months ended March 31, 2016, as well as an updated life of mine plan for its El Limón Guajes Mine ("ELG Mine" or "ELG").

Fred Stanford, President & CEO of Torex stated: "The team continues to exceed ramp-up expectations. Safety and environmental performance have been excellent, and production results have been consistently ahead of plan. With 19,900 ounces of gold produced in April, more than 1,000 ounces were produced per operating day. Above plan tonnages helped with this achievement, but above plan grades also made a significant contribution. The team is now entrenching the operating routines as we move toward 'steady state' at full production levels. Looking forward, the revised life of mine plan has a mine life that has been reduced to 8.5 years from 10 years. The team is putting the finishing touches on exploration plans that will seek to extend the mine life from a number of near mine targets."

HIGHLIGHTS

ELG Mine Achieved Commercial Production

  • On March 30, 2016, the Company announced that the ELG Mine had achieved commercial production ahead of schedule and under budget, reaching an average of more than 60% of design throughput of 14,000 tonnes per day ("tpd") for 30 days. For accounting purposes, the transition to the production phase will be reflected commencing April 1, 2016.

  • The plant produced 38,161 ounces of gold during the first quarter and produced 19,900 ounces of gold in April 2016.

  • Plant throughput was ahead of plan, averaging 9,100 tpd during the first quarter. In the latter half of April, throughput averaged more than 12,800 tpd, or 91% of design capacity, at an average gold recovery of 85%.

  • The current record daily production level of 16,300 tpd was achieved on May 9, 2016, and again on May 10. This exceeded nameplate design capacity of 14,000 tpd by 16%.

  • Gold recovery levels during the first quarter ranged from 63.0% to 90.7%, averaging above 80% for March 2016, compared to life of mine design levels of 87.4%.

  • The tailings filtration plant is delivering the expected product for dry stack disposal, and throughput has been steadily increasing to match the cadence set by the grinding circuit.

Mining

  • At the end of the first quarter, the Company had approximately 1.0 million tonnes of ore stockpiled.

  • Commissioning of both the El Limón crusher and RopeCon commenced in March 2016 and was completed in April.

  • The resettlement of the Real del Limón village was started during the first quarter and was completed in April 2016.