Silver Tiger Provides 2024 Summary and 2025 Outlook

In This Article:

Silver Tiger Metals Inc. (TSXV:SLVR) and (OTCQX:SLVTF) ("Silver Tiger" or the "Corporation") is pleased to provide a year-end review of 2024 highlights and a 2025 outlook for its 100% owned, silver-gold El Tigre Project (the "Project" or "El Tigre") located in Sonora, Mexico.

Key Objectives for 2025

  • With $7.0 million in cash on hand at September 30, 2024, we will complete the planned underground 5,000-meter drill program;

  • Continue drilling the high-grade Veins, Sulfide Zone and Shale Zone from underground drill pads, with the first drill results expected in January 2025;

  • Deliver a Preliminary Economic Assessment ("PEA") for the permitted underground resource during H1-2025;

  • Negotiations and due diligence are underway with lenders to secure project financing for the open pit portion of the Project; and

  • Make a construction decision upon receipt of the open pit permit.

2024 Highlights

  • Delivered a Preliminary Feasibility Study ("PFS") with base case After-Tax NPV of US$222 million, an After-Tax IRR of 40%, and a 2.0-year payback period (see Corporation's press release dated October 22, 2024);

  • Delivered updated Mineral Resource Estimate ("MRE") of the open pit Stockwork Mineralization Zone (see Corporation's press release dated October 22, 2024); and

  • Commenced drilling from underground drill pads on the high-grade Veins, Sulfide Zone and Shale Zone (see Corporation's press release dated December 3, 2024).

Glenn Jessome stated "As we wrap up 2024, I'm pleased to highlight the progress Silver Tiger has made this year. With the hard work of our team and the continued support of our shareholders, we've reached key milestones that position us for success in 2025. Our PFS for the open pit is complete, and we will continue to work to obtain project financing for the open pit portion of the Project. We have begun drilling the high-grade Veins, Shale Zone and Sulfide Zone from underground drill pads, as we work towards a PEA in H1-2025 for our underground resource."

Silver Tiger Announced PFS with NPV of US$222M for the Stockwork Zone

Silver Tiger announced a PFS on October 22, 2024. The PFS is focused on the conventional open pit mining economics of the Stockwork Mineralization Zone defined in the updated MRE.

Highlights of the PFS are as follows (all figures in US dollars unless otherwise stated):

  • After-Tax NPV (using a discount rate of 5%) of US$222 million with an After-Tax IRR of 40.0% and Payback Period of 2.0 years (Base Case);

  • 10-year mine life recovering a total of 43 million payable silver equivalent ounces ("AgEq") or 510 thousand payable gold equivalent ounces ("AuEq"), consisting of 9 million silver ounces and 408 thousand gold ounces;

  • Total Project undiscounted After-Tax Cash Flow of US$318 million;

  • Initial capital costs of $86.8 million, which includes $9.3 million of contingency costs, over an expected 18- month build, expansion capital of $20.1 million in year 3 and sustaining capital costs of $6.2 million over the life of mine ("LOM");

  • Average LOM operating cash costs of $973/oz AuEq, and all in sustaining costs ("AISC") of $1,214/oz AuEq or Average LOM operating cash costs of $12/oz AgEq, and AISC of $14/oz AgEq;

  • Average annual production of approximately 4.8 million AgEq oz or 56.7 thousand AuEq oz; and

  • Three (3) years of production in the Proven category in the Phase 1 Starter Pit.