Poplar Grove Operations Update

  • Significant increases in productivity rates are being achieved by the underground mine's first production unit

  • A peak mining rate of 306 ft was cut in a single shift during the week of 10 June

  • Additional productivity increases are expected in the coming weeks, with commissioning of the ventilation overcasts to allow both continuous mining machines to be operated concurrently

  • Mining has progressed beyond the initial challenging conditions caused by a paleochannel intersecting the mine workings

  • Realized bit costs for continuous miners and roof bolters are expected to be ~$1.5M p.a. lower than the BFS forecast due to softer than expected cutting and drilling conditions

  • Processing & surface operations are functioning well, with plant yield increasing as out of seam dilution decreases

  • Delivered coal quality is meeting or exceeding contract specifications

NEW YORK, NY / ACCESSWIRE / June 17, 2019 / Paringa Resources Limited ("Paringa" or "Company") (NASDAQ: PNRL, ASX: PNL) is pleased to provide an update on activities at the Poplar Grove mine in western Kentucky.

Underground mining operations

Underground mining activities undertaken by the first mining unit ("Unit 1"), comprising two continuous mining machines ("CMs"), are progressing well, with record productivity achieved in recent weeks. During the week of 10 June, the peak mining rate of 306 ft of material was cut in a shift, a 100% increase on the prior week.

Unit 1 has now completed the majority of bottom development, with construction of the ventilation overcasts being the only remaining project, expected to be commissioned in the coming weeks. Commissioning of the overcasts will allow the mining unit to be ventilated in a manner known as "split ventilation", allowing both CMs to operate concurrently. The ability to operate both CMs concurrently will result in a further significant productivity increase.

Softer than expected cutting conditions are leading to reduced consumption of bits for the CMs and roof bolters, as well as allowing the use of less expensive bits. The estimated costs savings are ~$1.5M p.a. when compared to the BFS forecast.

All underground and surface mobile equipment necessary for the operation of two mining units is onsite, and Paringa is in the process of hiring hourly employees in anticipation of commissioning Unit 2 over the coming months.

Mining productivity

A key measure of room and pillar mining productivity is the number of feet advanced per shift ("ft/shift"), with Paringa averaging a rate of ~200 ft/shift during the week of 10 June, which has steadily increased from an average of ~40 ft/shift when mining began in April.