ORVANA PROVIDES CONSTRUCTION UPDATE FOR DON MARIO, BOLIVIA AND REPORTS Q1 FY2025 PRODUCTION FROM OROVALLE, SPAIN

In This Article:

TSX:ORV

TORONTO, Jan. 16, 2025 /CNW/ - Orvana Minerals Corp. (TSX: ORV) (the "Company" or "Orvana") is pleased to provide a progress update for construction and financing activities at Don Mario (Bolivia) and to report production and exploration updates for the first quarter of fiscal year 2025 ("Q1 FY2025) ending December 31, 2024 from Orovalle (Spain).

Don Mario – Oxides Stockpile Project

  • The Company's Bolivian subsidiary, Empresa Minera Paitití, S.A. (EMIPA) has obtained key permits for the plant expansion at Don Mario and construction has commenced.

  • Construction activities to-date have focused on site preparations and earthworks for the plant expansion area, including the concrete foundation work.

  • Contracting and fabrication of structural steel, tanks and key process equipment is now underway.

  • All activities are advancing on schedule and as of December 31, 2024, the project is approaching 3.5% completion.

  • To-date, approximately 118,496 project hours have been worked and there have been no reportable injuries or environmental incidents.

  • There are currently 150 construction personnel at site.

  • Based on recent contractor and vendor quotations, the Company is updating capital cost estimates, and will provide updates when further material information becomes available.

  • The Company expects to complete construction by the end of calendar year 2025, conditional on securing the remaining required balance of the funding during the first half of 2025.

  • Further information about the project is contained in the Company's technical report dated March 15, 2022 entitled "National Instrument 43-101 Technical Report for the Don Mario Property, Eastern Bolivia," which is available under the Company's profile on SEDAR+ and on the Company's website.

Juan Gavidia, CEO of Orvana, commented, "We are pleased with progress through the first quarter of construction. The project is on track for commercial production by early 2026, which will be a transformative event for our Company."

Orovalle - Q1 FY2025 Production Results

  • 7,631 gold ounces produced, on track to meet fiscal year 2025 guidance of 37,000 - 41,000 Oz.

  • 1.1 million copper pounds produced, on track to meet fiscal year 2025 guidance of 2,400 – 2,700 K lbs.



Q1 FY2025

Q4 FY2024

Q1 FY2024

FY 2025 Guidance

Ore milled (tones)


118,649

139,275

130,267


Gold equivalent (oz)(1)


9,694

11,862

9,550


Gold






    Grade (g/t)


2.16

2.39

2.09


    Recovery (%)


92.7

92.5

91.5


    Production (oz)


7,631

9,888

7,994

37,000 - 41,000

Copper






     Grade (%)


0.48

0.41

0.32


     Recovery (%)


85.5

75.4

76.3


     Production (K lbs)


1,068

961

702

2,400 - 2,700

Silver






     Grade (g/t)


10.78

8.90

6.77


     Recovery (%)


81.0

75.0

72.0


     Production (oz)


33,306

29,864

20,393


(1) Gold Equivalent Ounces ("GEO") were calculated using the following average market prices:


Q1 FY2025: _$2,661.61/oz Au, $31.34/oz Ag, $4.16/lb Cu


Q4 FY2024: _$2,476.80/oz Au, $29.42/oz Ag, $4.17/lb Cu


Q1 FY2024: _$1,975.87/oz Au, $23.23/oz Ag, $3.71/lb Cu

GEO is a Non-GAAP Financial Performance Measure. For further information and detailed reconciliations, please see the "Non-GAAP Financial Performance Measures" section of the Company's FY2024 MD&A.