Orezone Provides Hard Rock Expansion Update for Its Bomboré Gold Mine

In This Article:

Orezone Gold Corporation
Orezone Gold Corporation

VANCOUVER, British Columbia, Oct. 24, 2024 (GLOBE NEWSWIRE) -- Orezone Gold Corporation (TSX: ORE, OTCQX: ORZCF) (“Orezone”) is pleased to provide an update on the hard rock expansion at its Bomboré Gold Mine. The hard rock expansion is forecasted to increase annual gold production to over 170,000 ounces, an approximate 50% increase from current levels, with first gold planned in Q4-2025.

Site works are well-advanced with the plant-site area cleared and all major earthworks complete. Laydown areas have been prepared and are ready to receive construction equipment, offices, and major plant deliveries. Camp upgrades for construction supervision and teams are also now operational.

Engineering and Procurement

Lycopodium Minerals Canada (“Lycopodium”) was awarded the engineering and procurement contract and is ahead of schedule on both activities. Lycopodium was selected due to their successful track record of designing and constructing numerous gold plants in West Africa, including the Company’s Phase I oxide plant that is currently in operation and exceeding nameplate design.

In terms of procurement, the Company has placed over 50% of all packages including CIL tank platework and 95% of all process equipment. This includes the purchase of a 9MW 26’ diameter SAG mill. The SAG mill is a new, pre-owned mill that was never installed and carries a full warranty by the supplier. Substantial savings in costs and schedule are being realized from the purchase of this manufactured mill. The mill shells, heads and ring gear are now being packaged for shipment later this quarter which is well ahead of schedule.

Site Construction Activities

The concrete installation contract was recently awarded with mobilization of the batch plant and equipment scheduled for mid-November, three months ahead of schedule.

The tank platework supply was awarded in September, and bids for the structural steel and general platework are under evaluation and will be awarded in November.

The main Structural, Mechanical, and Piping installation contract is expected to be awarded in Q1-2025, which again will be ahead of schedule.

Mining Fleet and Explosives Magazine

The first shipment of the hard rock fleet by the mining contractor, which includes new trucks and excavators, has arrived in Burkina Faso and will be transported to site in late October. This early delivery will allow for systematic training of operators well ahead of the start of hard rock mining and will facilitate more cost-effective mining of the lower transition material in the near-term. The remaining hard rock fleet will be delivered to site over the coming six to eight months.