Northland Resources Operational Update-November 2012

LUXEMBOURG, LUXEMBOURG--(Marketwire - Nov 21, 2012) - Northland Resources S.A. (NAU.TO)(NPK.F)(NAUR.OL)(NAURO.ST) ("Northland" or the "Company") announces its fifth bi-monthly operational and construction update on the Kaunisvaara project. During this period, September 25 - November 21, Northland completed its first ore blast, received dispensation for 90 tonnes trucks and completed the installation of the primary crusher, which is now fully operational.

  • The schedule for the Kaunisvaara project remains unchanged, with concentrate production from the Tapuli Mine scheduled to commence at the end of November 2012, with shipments of concentrate from the Port of Narvik starting early in first quarter 2013.

  • The first Kaunisvaara process line was 95% complete at the end of October and remains on schedule.

  • Cold commissioning of the process plant has commenced.

  • The primary crusher is now installed and the feeding of ore into the stockpile building has commenced.

  • The first ore blast of 90,000 tonnes of iron ore and 320,000 tonnes of waste rock was completed October 18.

  • Dispensation was granted by the STA for the use of trucks with a gross weight of 90 tonnes.

  • The Company plans to produce 1.4 dmt1 in 2013 and to reach the production capacity of 4.0 dmtpa2 in the beginning of third quarter of 2014.

THE MINE AND PROCESS PLANT

  • The first Kaunisvaara process line is 95% complete, and remains on schedule. The second Kaunisvaara process line is 56% complete as of October 31. Cold commissioning is ongoing according to plan and with no major issues reported.

  • The Sahavaara mine and related investments are 35% complete.

  • Work on the Tapuli primary crusher is complete and in-line with contract scope.

  • The truck workshop is now in use by PonCat.

  • All works on the Tapuli stockpile building are complete.

  • All works on the grizzly building are complete.

  • Conveyor belts are installed from the Tapuli Mine to the process plant through the grizzly building.

THE LOGISTICS CHAIN

  • Northland has, together with Cliffton Mining ("Cliffton") and truck manufacturer Scania AB ("Scania"), carried out trial runs with a vehicle of 90 tonnes gross weight to optimize the future traffic flow on the road between Kaunisvaara and Pitkäjärvi. The trial runs were successful and the Swedish Transport Administration ("STA") has now decided to grant Northland dispensation to use trucks with a gross weight of 90 tonnes instead of the Swedish standard of 60 tonnes. The dispensation applies from November 2012 until October 2013. The dispensation has to be renewed each year in accordance with standard procedure. The build-out of the logistics chain is on schedule for the commencement of deliveries to customers early in the first quarter of 2013.

  • Road and rail interchange work is on schedule.

  • The Swedish government intends to invest in improved infrastructure in the County of Norrbotten. Among other measures, new resources will be allocated to increase the capacity of the Malmbanan, the "Ore Railway". A further SEK 1.3 billion is earmarked for the road between Pajala and Pitkäjärvi/Svappavaara, along which Northland''s iron ore concentrate will be transported. 30 km has already been upgraded during 2012.

  • Kiruna Wagon is currently manufacturing the railcars contracted by Northland in accordance with the contracted time schedule. To allow for a quicker production ramp-up, the Company will during an initial period rent additional rail cars from a third party supplier.