NextDecade Provides Third Quarter 2024 Business Update

In This Article:

HOUSTON, November 07, 2024--(BUSINESS WIRE)--NextDecade Corporation (NextDecade or the Company) (NASDAQ: NEXT) today provided an update on developmental and strategic activities for the third quarter and early fourth quarter 2024.

CEO Commentary

"We continued to make excellent progress on the construction of Phase 1 at the Rio Grande Facility during the third quarter," said Matt Schatzman, NextDecade’s Chairman and Chief Executive Officer. "The facility continues to progress safely, in line with schedule, and on budget, and the site has significantly advanced in the past few months. The Bechtel team has done exemplary work, including continued pipe work for Train 1, completing the first foundation pour for Train 2, and preparing to begin deep soil mixing for Train 3. Bechtel has also laid feed gas piping and begun constructing walls for both storage tanks. We remain committed to working with Bechtel to prioritize safety and risk management as Phase 1 construction continues."

"We have been managing the D.C. Circuit Court’s August decision to vacate the reauthorization of the Rio Grande LNG Facility with our partners and stakeholders, and we would like to thank the local Rio Grande Valley community, numerous local and federal elected officials, our LNG customers, our lenders, our equity partners, the Brownsville Navigation District, Bechtel, our suppliers, many industry participants and groups, and all other stakeholders for their widespread support of the Rio Grande LNG project and the Company. In October, we filed a petition for rehearing and rehearing en banc with the Court. The Court’s decision will not become effective while the appeals process is ongoing, and we remain committed to taking any and all available legal and regulatory actions to ensure that Phase 1 will be delivered on time and on budget and that FID on Trains 4 and 5 will not be unduly delayed."

Significant Recent Developments

Construction

  • Under the EPC contracts with Bechtel Energy Inc. (Bechtel), Phase 1 progress is tracked for Train 1, Train 2, and the common facilities on a combined basis and Train 3 on a separate basis. As of September 2024:

    • The overall project completion percentage for Trains 1 and 2 and the common facilities of the Rio Grande LNG Facility was 30.5%, which is in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 76.1% complete, procurement was 57.6% complete, and construction was 5.5% complete.

    • The overall project completion percentage for Train 3 of the Rio Grande LNG Facility was 9.8%, which is also in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 17.0% complete, procurement was 21.9% complete, and construction was 0.1% complete.