NextDecade Provides Fourth Quarter 2024 Business Update

In This Article:

Outlines Development Plans for Approximately 18 MTPA of Additional Liquefaction Capacity

HOUSTON, February 28, 2025--(BUSINESS WIRE)--NextDecade Corporation (NextDecade or the Company) (NASDAQ: NEXT) today provided an update on developmental and strategic activities for the fourth quarter 2024 and early first quarter 2025.

CEO Commentary

"As we begin 2025, we are at an exciting time in NextDecade history. Our team is working diligently to capitalize on our outsized growth opportunities while continuing to construct Trains 1 through 3 (Phase 1) at the Rio Grande LNG Facility safely, on schedule, and on budget," said Matt Schatzman, NextDecade’s Chairman and Chief Executive Officer. "We are working with multiple potential commercial counterparties to progress Trains 4 and 5 toward positive final investment decisions (FIDs), and we believe we are well positioned to secure commercial support for both trains."

"Today, we are also pleased to announce development plans for expansion capacity at the Rio Grande LNG Facility site beyond Trains 1 through 5. We are currently developing and preparing to start the permitting process for Train 6 and starting the development of Trains 7 and 8. Train 6 is being developed inside the existing levee at the site, which is expected to provide advantages in site preparation and expected economics. We plan to pre-file an application with the Federal Regulatory Energy Commission (FERC) for Train 6 this year. Trains 7 and 8 are being developed on the site outside of the existing levee. Additionally, we expect to explore options for the development of up to two additional trains at our site beyond Train 8."

Significant Recent Developments

Construction

  • Under the EPC contracts with Bechtel Energy Inc. (Bechtel), Phase 1 progress is tracked for Train 1, Train 2, and the common facilities on a combined basis and Train 3 on a separate basis. As of January 2025:

    • The overall project completion percentage for Trains 1 and 2 and the common facilities of the Rio Grande LNG Facility was 38.1%, which is in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 84.9% complete, procurement was 69.2% complete, and construction was 10.6% complete.

    • The overall project completion percentage for Train 3 of the Rio Grande LNG Facility was 15.3%, which is also in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 33.5% complete, procurement was 32.8% complete, and construction was 0.4% complete.

  • In February 2025, the Company provided additional information regarding its development of additional liquefaction capacity at the Rio Grande LNG Facility beyond Trains 1 through 5. Trains 6 through 8 are wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 MTPA once constructed and placed into operation.

    • Train 6, with expected LNG production capacity of approximately 6 MTPA, is being developed inside the existing levee at the site and adjacent to Trains 1 through 5. A pre-filing application with FERC for Train 6 is expected in 2025, and a full FERC application is expected in early 2026.

    • Trains 7 and 8, with a total expected LNG production capacity of approximately 12 MTPA, are being developed on the site outside of the existing levee.