EDMONTON, ALBERTA--(Marketwired - Jul 10, 2014) - North Country Gold Corp. (TSX VENTURE:NCG)(NCGDF) ("North Country", "NCG" or the "Company") today announced the Company has completed a review of the existing combined open-pit/underground resource estimate for the Three Bluffs Gold Deposit published in April 2013 and is pleased to highlight a potential high-grade underground subset contained within the current estimate, which the Company considers to demonstrate the potential existence of a conceptual high-grade underground deposit at Three Bluffs.

"From the results of our high-level trade off analysis and logistical studies announced January 22, 2014, and North Country's belief that the Three Bluffs Gold Project may be suited to a possible medium sized operation which focusses on coherent trends of high grade gold mineralization, this subset of the resource estimate clearly demonstrates the presence of considerable high grade components to the deposit", stated Brian Budd, President of North Country Gold. "Our ongoing work programs will continue to upgrade our geological knowledge of these structures as we pursue strategies to potentially grow the present high-grade resource base and advance the project towards preparation of a possible PEA" added Mr. Budd.

High-Grade Subset

Utilizing an overall block cut-off grade of 5.0 g/t, which the company believes better reflects underground mining costs at these deposits and at this location, a possible high-grade underground subset of the existing Three Bluffs resource estimate contains an indicated resource of 1.140 Mt grading 11.21 g/t Au for 411,000 ounces gold and an inferred resource of 1.900 Mt grading 9.15 g/t for 558,000 ounces gold.

Table 1 summarizes the current Three Bluffs resource estimate queried at a 5.0 g/t grade cut-off, which is a high-grade underground subset of the existing combined open pit and underground resource estimate previously released April 23, 2013 as summarized in Table 2 below.

Table 1. Three Bluffs Resource Estimate* (Subset of April 2013 resource estimate)

High Grade Underground* - 1.0 g/t Au Model

Classification

Grade Cut-off
g/t

Tonnage
Tonnes

Au
g/t

Au
ounces

Indicated

5.00 g/t

1,140,000

11.21

411,000

Inferred

5.00 g/t

1,900,000

9.15

558,000

(See footnotes below Table 2)

Three Bluffs Gold Deposit

The Three Bluffs gold project is a structurally controlled lode gold system hosted within oxide facies iron formation and greywackes. The deposit currently hosts an open-pit/underground resource of 4.30 Mt at 4.91 g/t gold for 683,000 ounces gold (indicated) and 5.52Mt at 5.43 g/t gold for 965,000 ounces gold (inferred) using a cut-off grade of 1.35 g/t for open pit (inside Whittle shell) and a cut-off grade of 2.5 g/t for underground (outside Whittle shell) (See press release dated April 23, 2013, Table 2, and applicable notes).