Mart Resources, Inc.: Operations and Production Update

CALGARY, ALBERTA--(Marketwired - Aug 12, 2013) - Mart Resources, Inc. (TSX VENTURE:MMT) ("Mart" or the "Company") and its co-venturers, Midwestern Oil and Gas Company Plc. (Operator of the Umusadege field) and SunTrust Oil Company Limited are providing the following updates on Umusadege field production for July 2013, the UMU-11 well, status of a second drilling rig, and Umugini pipeline construction.

July 2013 Production Update

Umusadege field production during July 2013 averaged 10,800 bopd. Umusadege field downtime during July 2013 was approximately 4.5 days due to sporadic shutdowns required for commissioning and testing of the new central processing facility and operations connected to preparation for drilling of the UMU-11 well. The average field production based on producing days was 13,200 bopd in July 2013, which is the highest average daily production rate for a calendar month based on production days realized from the Umusadege field.

Total net crude oil deliveries into the export pipeline from the Umusadege field for July 2013 were approximately 347,100 bbls before pipeline losses. Pipeline and export facility losses for May 2013, June 2013 and for July 2013 have not yet been reported by the export pipeline operator, Nigerian Agip Oil Company ("Agip"). In the past, Agip has reported pipeline and export facility losses one month after the final reporting of each month's injection totals, but for the past two months the pipeline losses have not been reported. Mart and its co-venturers have requested the loss information from Agip and will release this information as soon as it is received.

As a result of negotiations with Agip, the Umusadege field has been allocated an additional pipeline reserved production capacity of 4,500 bopd. An increase in oil shipments from the Umusadege field will be achieved after more powerful pumps are obtained and installed by Agip.

UMU-11 Well Update

The drilling rig was skidded ahead, and new 20-inch conductor pipe has been pile driven to a final depth of 330 feet. The conductor pipe will be cleaned out and secured, and drilling operations are expected to commence shortly thereafter.

After completion of the UMU-11 well, an exploration/appraisal well is planned to be drilled on the East exploration structure.

Second Drilling Rig

A tender for a second drilling rig was successfully completed, and after site preparation the second drilling rig is expected to start drilling a water disposal well in September 2013. After completion of the water disposal well, the drilling rig will move to the UMU-4 location to drill a re-entry horizontal development well. Mart and its co-venturers plan to drill several additional horizontal wells in the Umusadege field.