Lion One Releases Financial Results for Quarter Ended September 30, Announces USD $4 Million Tranche 3 Draw down on Nebari Financing Facility

In This Article:

North Vancouver, British Columbia--(Newsfile Corp. - December 2, 2024) - Lion One Metals Limited (TSXV: LIO) (OTCQX: LOMLF) (ASX: LLO) ("Lion One" or the "Company") is pleased to release the Company's financial results for Q1 FY 2025, and announces that the Company has entered into an agreement to amend certain terms and draw down a further USD $4,000,000 ("Tranche 3") of its Senior Secured Financing Facility (the "Financing Facility") provided by Nebari.

Financial Highlights Q1-FY25

During the three-month period ended September 30, 2024, the Company achieved the following:

  • Mine operating income of CAD$1,529,978

  • Record revenue of CAD$10,468,452

  • 3,129 ounces (oz) of gold sold, and 1,093 oz of silver sold

  • Average realized gold selling price of CAD$3,332 per oz

  • Cost of sales per gold oz of CAD$2,843 (net of silver revenue)

Mine Operations Highlights Q1-FY25

During the three-month period ended September 30, 2024, the Company achieved the following mining physicals:

  • Total 54,829 tonnes mined

  • 21,852 tonnes of waste mined

  • 32,977 tonnes of mineralized material mined at average grade of approximately 4.83 Au g/t

  • Total capital development of 283 meters

  • Total operating development of 666 meters

  • Decline advancement of 163 meters and vertical development of 155 meters

Mine production during the quarter was impacted by mine equipment availability in July and August as two underground loaders and a single boom jumbo were out of service for repairs. A new underground loader arrived on site in September resulting in improved equipment availability. Despite the mine equipment utilization issues, the mine was still able to deliver 32,977 tonnes of mineralized materials at 4.83 g/t Au, including 28,922 tonnes of mineralized materials at 5.16 Au g/t and 4,055 tonnes of lower grade mineralized materials at 2.46 Au g/t. The Company will stockpile the lower grade materials (mineralized materials below 3 Au g/t) with the intention of feeding the lower grade mineralized materials once the mill expansion has been completed and excess milling capacity is available.

In the near term, the Company will continue to add mining equipment to improve equipment availability and invest in critical mine infrastructure projects such as the raise bore and mine ventilation project which started in October 2024 and scheduled for completion in January 2025.

Pilot Plant Operations Highlights Q1-FY25

During the three-month period ended September 30, 2024, the Company achieved the following mill physicals:

  • 31,391 tonnes of mineralized material processed at an average head grade of 4.6 Au g/t

  • Record 3,639 oz of gold recovered

  • 2,889 oz gold doré poured

  • 3,129 oz gold refined and sold

  • Overall 78.2% recovery achieved for the quarter

  • Record 81.3% recovery achieved in September

  • 81 days of mill operations in the quarter

  • 11 days of mill downtime, including 9 days for scheduled mill maintenance

  • Approximately 1,889 oz of mineralized material (primarily gold) was retained within the mill circuit as in process store of metal as of September 30, 2024, with an additional 112 oz of gold doré stored in inventory.