Unlock stock picks and a broker-level newsfeed that powers Wall Street.
Kirkland Lake Gold Inc.: Fiscal 2014 First Quarter Operating Results

KIRKLAND LAKE, ONTARIO--(Marketwired - Aug 22, 2013) - Kirkland Lake Gold Inc. (the "Company") (TSX:KGI)(AIM:KGI), an operating and exploration gold mining company, announces operational results for the first quarter of fiscal 2014 (May, June, July, 2013).

During the first quarter, 97,788 tons were produced at a head grade of 0.3246 ounces per ton ("opt") and a recovery rate of 95.04% to produce 30,316 ounces of gold. Ore tonnage produced was a quarterly record and the average daily ore tonnage rate of 1,063 tons per day was a record as well. Sold ounces for the quarter were 30,253 at an average sales price of $1,426 per ounce.

Notwithstanding the record ore tonnage rates, production was impacted during the quarter by a number of planned shutdowns related to the work required to increase the mine hoisting capacity and the capacity of the processing plant. This impact had been outlined in the Company's year end Management Discussion and Analysis document. During these shutdowns, work was completed that was required to increase the average mine hoisting capacity to 2,200 tons per day, including replacing the 10.0 ton skips with 12.5 ton skips, and to optimize the existing mill grinding circuit and bring the new crushing circuit on line. The estimated impact of these shutdowns was 2-3 weeks of normal production over the quarter, which was slightly longer than expected. As a result, the production tonnage was 4.6% under planned production for the quarter.

The head grade for the year is expected to fluctuate between 0.30 opt and 0.40 opt, dependant on the availability of higher grade ore mining workplaces in the mining sequence. Recovery was low in the first quarter due to circuit disruptions related to unexpected power disruptions caused by outside factors, and due to issues related to working with new equipment.

The processing plant will be impacted this year by several planned shutdowns required to bring other new equipment on line. These shutdowns may affect the timing of production, but should not affect overall production, as the remaining processing plant upgrades are off the critical path. A planned shutdown of the hoisting plant in August has been eliminated due to the updated work plan and to more work than expected being completed in the first quarter. The remaining hoisting plant upgrades are no longer on the critical path, as demonstrated by the establishment of a new record hoist of over 2,800 tons of ore and waste being hoisted in a single day (approximately 19 hours of hoisting).

Sixty-two ore mining workplaces are currently in the production mining cycle, with thirty-two additional workplaces being developed (Q4:49 mining workplaces and 21 workplaces being developed). The number of ore mining workplaces in the cycle is expected to increase to approximately one hundred over the next year, as additional miners are hired and trained and as these additional workplaces are developed and brought on line. These activities are the critical path activities for the remainder of the mine expansion project.