Kiniero on Track for First Gold in Q4 2025

In This Article:

Robex Resources Inc.
Robex Resources Inc.

Highlights:

  • First gold pour is on track for Q4 2025, key long lead items procured

  • Project Development team appointed, led by Chief Development Officer Dimitrios Felekis

  • Engineering for doubling plant capacity to 6Mtpa was awarded to Primero Engineering and is currently 24% complete

  • Additional Ball Mill awarded and scheduled for shipment in May 2025, SAG Mill on track for Q1 2025

  • Power station awarded with delivery from May 2025

  • Tailings Storage Facility (TSF) expanded design commenced with Knight Piésold

  • Civils contracts awarded, and concrete work has recommenced on site

  • Earthworks Fleet for TSF and infrastructure arrived in Guinea

  • Electrical and instrumentation awarded to ECG Engineering

  • Inferred resource drilling program for Mansounia nearing completion with more than 32,000 metres of RC and more than 2,600 meters of DD completed

  • Updated Feasibility Study for Kiniero on track for Q1 2025, led by AMC.

QUEBEC CITY, Oct. 08, 2024 (GLOBE NEWSWIRE) -- West African gold producer and developer Robex Resources Inc (“Robex” or the “Company”) (TSXV: RBX) is pleased to provide a project development update for Kiniero Gold Project in Guinea. The project is on track for first gold in Q4 2025.

Robex Managing Director Matthew Wilcox said: “I am very pleased to provide shareholders with our first project development update for Kiniero with the expanded project, nearly doubling the previous plant size.

With our recent capital raise, we have been able to advance the schedule to leverage Kiniero’s potential to be one of the largest and lowest cost gold producing mines in Guinea.

We will provide regular updates as we track towards first gold by the end of Q4 CY25 as construction advances the Kiniero Gold Project to become West Africa’s next gold mine.”

DEVELOPMENT TEAM APPOINTMENTS

Dimitrios Felekis – Chief Development Officer

Dimitrios has joined the Robex team as Chief Development Officer from Primero Engineering after serving as Project and Design manager on Tietto Minerals’ Abujar project in Côte d’Ivoire. He has more than 25 years of experience primarily in the design and development of West African gold projects, including 17 years with Lycopodium Engineering. Dimitrios has worked on multiple West African gold projects including his role as Design Manager and Lead Field engineer on Nordgold’s Bissa and Bouly Project in Burkina Faso.

Daniel Kotzee – Construction Manager

Daniel joins the team from Tietto Minerals where he was most recently the Construction Manager of the 5Mtpa Abujar gold project. Daniel has more than 15 years’ experience in gold project development, including roles as construction manager of the Sanbrado gold project in Burkina Faso for West African Resources, Nordgold’s Gross project in Southern Yakutia, as well as roles in both the Bissa and Bouly projects in Burkina Faso. Daniel also spent more than 12 months at Nordgold’s Lefa Gold Operation in Guinea as project superintendent.