Unlock stock picks and a broker-level newsfeed that powers Wall Street.

Ivanhoe Mines Confirms Kamoa-Kakula Achieved a Record 50,176 Tonnes of Copper Production in April

In This Article:

Monthly production record achieved over 30 days, Kamoa-Kakula hits an annualized copper production rate of approx. 625,000 tonnes at the end of April

Phase 3 concentrator achieves record throughput rates at 20% above nameplate capacity during Q1, equivalent to an annualized milling rate of 6.1 million tonnes per annum

Further improvements in Phase 3 copper grade, milling performance and improved power stability expected to drive additional production growth over the remainder of 2025

Africa's largest and greenest direct-to-blister copper smelter well on track to produce first anode in July, projected to improve operating margins

Kolwezi, Democratic Republic of Congo--(Newsfile Corp. - May 2, 2025) - Ivanhoe Mines (TSX: IVN) (OTCQX: IVPAF) Executive Co-Chairman Robert Friedland and President and Chief Executive Officer Marna Cloete announced today that the Phase 1, 2, and 3 concentrators at the Kamoa-Kakula Copper Complex in the Democratic Republic of the Congo (DRC) achieved a monthly combined production record of 50,176 tonnes of copper in concentrate during the 30 days of April. The concentrators milled 1.35 million tonnes of ore at an average feed grade of 4.19% copper during the month.

The recently ramped-up Phase 3 concentrator achieved an average recovery rate of 87.4% during April, exceeding its design rate of 86%. Since mid-March, total copper production has notably risen to an average of approximately 12,000 tonnes per week, as shown in Figure 1. The outperformance is equivalent to an annualized production rate of approximately 625,000 tonnes per annum, approximately 12% higher than the midpoint of 2025 guidance.

The outperformance was underpinned by initiatives implemented earlier in the first quarter that enabled the Phase 3 concentrator to be consistently fed at higher rates than originally designed. Phase 3 milled a record 1.51 million tonnes of ore during the first quarter. The record is equivalent to an annualized milling rate of 6.1 million tonnes per annum, which is more than 20% higher than the Phase 3 concentrator's design capacity of 5.0 million tonnes per annum.

Kamoa-Kakula reached a major turning point during the quarter, following a significant increase in imported hydroelectric power that provided Kamoa-Kakula's management team with the confidence to finalize commissioning and commence the start-up of the smelter. The start-up of the new on-site copper smelter is expected in the coming weeks.

During the first quarter, the total average power required for the Phase 1, 2, and 3 operations was between 130 MW and 140 MW. At the beginning of March, Kamoa-Kakula was drawing 50 MW of domestically generated hydroelectric power, with 50 MW of hydroelectric power drawn from imported sources. The balance of required power was provided by on-site, diesel-generated backup power, of which there is an installed capacity of approximately 160 MW. Power drawn by the smelter is expected to gradually increase from 45 MW, following first feed of concentrate, up to 70 MW once at full capacity.