Ithaca Energy Inc.: Second Quarter 2016 Operations Update

ABERDEEN, UNITED KINGDOM--(Marketwired - Jul 11, 2016) - Ithaca Energy Inc (TSX: IAE) (LSE: IAE)

TSX: IAE

Not for Distribution to U.S. Newswire Services or for Dissemination in the United States
This Announcement Contains Inside Information

Ithaca Energy Inc.

Second Quarter 2016 Operations Update

11 July 2016

Ithaca Energy Inc. (TSX: IAE, LSE AIM: IAE) ("Ithaca" or the "Company") provides an operations update following the end of the second quarter of the year ("Q2-2016" or the "Quarter"), including an update on the status of the "FPF-1" floating production facility modifications programme being undertaken by Petrofac in the Remontowa shipyard in Poland. The Company is scheduled to issue its financial results for the first six months of the year ("H1-2016") on 15 August 2016.

Les Thomas, Chief Executive Officer, commented:
"The FPF-1 works are now being finalised, with preparation and performance of the inclination test being the only work required prior to the vessel exiting the yard. We are delighted with the quality and completeness of the vessel, having achieved our key objective of completing the onshore scope in the yard and avoided costly carry over of unfinished work offshore. Our existing production business is performing well, with volumes running ahead of guidance and continued deleveraging being delivered ahead of Stella start-up."

Greater Stella Area Development
The FPF-1 modifications are essentially complete and the vessel will be ready to leave the yard upon completion of approximately two weeks of work that is required to prepare for and perform the planned vessel inclination test and loading of supplies for the transit from the yard. Importantly, the onshore modifications scope has been completed in the yard without the need to carry onshore scope offshore. The FPF-1 is expected to leave the yard later this month and will complete the final marine system trials offshore Gdansk prior to being towed to the field. The anticipated period from sail-away to first hydrocarbons is approximately three months.

Further updates will be provided once the FPF-1 has left the yard and when it commences the tow to the field.

Production & Operations
The producing asset portfolio has performed well over H1-2016, with production running ahead of guidance. Average production during the Quarter was approximately 9,800 boepd, resulting in average production in H1-2016 of 9,400 boepd.

The remedial works on the Pierce field subsea gas injection flowline were completed as planned at the end of the Quarter and unrestricted production rates have been restored.