Horizonte Minerals PLC Announces Araguaia Construction Update

In This Article:

CONSTRUCTION OF THE ARAGUAIA NICKEL PROJECT REMAINS ON-BUDGET AND ON-SCHEDULE

HIGHLIGHTS:

  • Araguaia Nickel Project Line 1 remains on-schedule for production in Q1 2024 with over 50% of the construction programme completed to date

  • Strong safety performance, no lost time injuries with over two million hours worked

  • Earthworks are complete and detailed engineering is 95% complete

  • Key long lead items remain on track, with the rotary kiln and dryer en route to site

  • Pre-stripping activities have commenced on the main Pequizeiro Pit with ore stockpiling to begin in Q3 2023

  • Araguaia Nickel Project Line 1 remains on-budget with 90% of the total capital awarded as at 31 March 2023

  • Araguaia Nickel Project line 2 Feasibility Study, which aims to double nickel production from 14,500 tonnes per annum to 29,000 tonnes per annum, remains on track for publication in H2 2023

LONDON, UK / ACCESSWIRE / April 24, 2023 / Horizonte Minerals Plc (AIM:HZM)(TSX:HZM) ("Horizonte" or the "Company")reports that it is continuing to make good progress on the construction of its 100%-owned Araguaia Nickel Project Line 1 ("Araguaia" or "the Project") in Brazil, which remains on-budget and on-schedule to commence production in Q1 2024.

As of 30 March 2023, approximately 50% of the Araguaia Line 1 construction programme had been completed and approximately 90% of capital expenditure had been awarded, amounting to approximately US$485 million. Moreover, the earthworks have been completed, detailed engineering works are at 95% maturity, and electro-mechanical installations are advancing. The key long lead items remain on schedule for delivery to site, with the rotary kiln and dryer in Brazil and currently en route to site. In addition, the grade control drilling programme has been completed with the data utilised for the short term mining planning and the commencement of pre-stripping activities on the main Pequizeiro Pit, with ore stockpiling to begin in Q3 2023.

In addition to advancing the Araguaia construction activities, Horizonte is also making good progress on advancing its growth pipeline. The Araguaia Line 2 Feasibility Study ("FS"), which aims to double nickel production from 14,500 tonnes per annum to 29,000 tonnes per annum and allow Araguaia to not only produce high-grade low impurity ferronickel but also potentially nickel matte that can be upgraded to feed directly into the electric vehicle battery chemistry supply chain, remains on track for publication in H2 2023. Regarding Horizonte's 100% owned Vermelho project in Brazil, which is expected to produce 24,000 tonnes of nickel and 1,250 tonnes of cobalt to supply the EV battery market, work remained centred on the FS and the EIA permitting process, with the FS due for completion in H1 2024.