Gunnison Copper Provides a Construction Update for the Johnson Camp Mine in Southeast Arizona

In This Article:

Phoenix, Arizona--(Newsfile Corp. - March 21, 2025) - Gunnison Copper Corp. (TSX: GCU) (OTCQB: GCUMF) (FSE: 3XS) ("Gunnison" or the "Company") is pleased to provide a construction update for the fully permitted Johnson Camp Mine ("JCM"), in southeast Arizona.

Further to the last update where it was announced the mining fleet had been mobilized, and mining activities such as pre-stripping had begun (see Gunnison news release dated December 16th), the Company is pleased to report JCM construction activities are progressing well and on track to produce cathode in Q3 2025.

Mining of mineralized material commenced in January 2025 (Figure 1) and is being stockpiled in advance of the completion of the leach pad. Leach pad phase-1 is complete, and phase-2 of the leach pad follows closely behind (Figure 2). With phase-2 advancement we will begin installing Nuton's processing equipment and ultimately start stacking sulfide and oxide production mineralized material. The Company has completely redesigned and constructed a modern laboratory for on-site material and process analysis (Figure 3). The lab will begin ramping up in April and will be commissioned once production from the leach pad commences. In addition, the Company's HR group is progressing with its staffing plan, with a focus on hiring locally, and has added exceptional talent to the Gunnison team.

Figure 1 - Blast Hole Drill Rig Preparing a Bench for Mining at JCM

To view an enhanced version of this graphic, please visit:
https:/https://finance.yahoo.com/images.newsfilecorp.com/files/2744/245498_dd6e6b8f74ca19a8_001full.jpg

Figure 2 - Leach Pad Overhead View, 8 million square feet with dimensions of approximately 1220m by 640m. Phase 1 shows the protective, crushed rock, over-liner material on bottom half of the image and Phase 2 shows the black under-liner material with over-liner being placed on top.

To view an enhanced version of this graphic, please visit:
https:/https://finance.yahoo.com/images.newsfilecorp.com/files/2744/245498_dd6e6b8f74ca19a8_002full.jpg

"The fast pace at which our construction partners continue to progress the Johnson Camp project is nothing short of impressive. In roughly 12 months we will have transformed Gunnison Copper into a nimble open pit copper producer with a future as bright as the Arizona sky we enjoy daily," noted Robert Winton, SVP Operations of the Company.

Figure 3 - Newly Constructed Material and Process Analysis Laboratory

To view an enhanced version of this graphic, please visit:
https:/https://finance.yahoo.com/images.newsfilecorp.com/files/2744/245498_dd6e6b8f74ca19a8_003full.jpg