Gunnison Copper Mobilizes Mining Fleet at the Johnson Camp Mine in SE Arizona

In This Article:

Phoenix, Arizona--(Newsfile Corp. - December 16, 2024) - Gunnison Copper Corp. (TSX: GCU) (OTCQB: GCUMF) (FSE: 3XS) ("Gunnison" or the "Company") is pleased to provide a construction update for the fully permitted Johnson Camp Mine ("JCM"), in southeast Arizona, with first copper production anticipated mid 2025.

Further to the construction update from the press release dated August 8th, 2024, where it was announced construction of the new leach pad, including crushing of the over-liner material, had commenced the Company is pleased to report that the mining fleet has been mobilized, and mining activities such as pre-stripping have begun.

Construction of the Johnson Camp Mine is fully funded by Nuton LLC ("Nuton"), a Rio Tinto venture. Gunnison is the owner and operator of the mine which has a production capacity of up to 25 million pounds of copper cathode per year to directly supply critical American supply chains in the clean energy, defense, and manufacturing sectors.

"We are extremely pleased with how well the JCM construction is progressing. We are tracking our major construction milestones and budget, including mobilization of the mining fleet and leach pad construction. The successful start of mining activities was made possible by our highly talented local workforce of over 150 employees and third party contractors, reflecting our commitment to workforce development and local area economic stimulus," comments Robert Winton, SVP Operations and General Manager of Gunnison Copper. "From concept to first production measured in months is a testament to our partnership with Nuton and the support of the 3 engineering firms contributing to this industry first."

Phase 1 Pad Liner installation (Nov 21/24)

To view an enhanced version of this graphic, please visit:
https:/https://finance.yahoo.com/images.newsfilecorp.com/files/2744/233903_1aa5abe304166a51_002full.jpg

Ore control drilling in Burro Pit (December 10/24)

To view an enhanced version of this graphic, please visit:
https:/https://finance.yahoo.com/images.newsfilecorp.com/files/2744/233903_gunnison002.jpg

During construction, progress along with an image gallery will be posted on the company website at www.GunnisonCopper.com

ABOUT GUNNISON COPPER

Gunnison Copper Corp. is a multi-asset pure-play copper developer and producer that controls the Cochise Mining District (the district), containing 12 known deposits within an 8 km economic radius, in the Southern Arizona Copper Belt.

Its flagship asset, the Gunnison Copper Project, has a measured and indicated mineral resource containing over 831 million tons with a total copper grade of 0.31% (measured mineral resource of 191.3 million tons at 0.37% and indicated mineral resource of 640.2 million tons at 0.29%), and yielding robust economics including an NPV8% of $1.3Billion, IRR of 20.9%, and payback period of 4.1 years. It is being developed as a conventional operation with open pit mining, heap leach, and SX/EW refinery to produce finished copper cathode on-site with direct rail link.