Grande Portage Resources Develops Conceptual Mining Plan

In This Article:

VANCOUVER, BC / ACCESSWIRE / September 9, 2024 / Grande Portage Resources Ltd. (TSXV:GPG)(OTCQB:GPTRF)(FSE:GPB) ("Grande Portage" or the "Company") is pleased to announce that, further to its recently filed updated **NI #43-101 Mineral Resource Estimate, the Company has developed a Conceptual Mining Plan to determine the optimal development pathway for its Herbert Gold project located in SE Alaska.

To that end, earlier this year, the Company engaged the services of OreLogic LLC, a consulting firm providing mine planning and project development services. OreLogic is led by Kyle Mehalek, formerly Chief Mining Engineer at Hecla Mining's Greens Creek Mine in southeast Alaska, one of the largest and lowest-cost primary silver mines in the world.

The Company's gold deposit, formerly known as the Herbert Gold project, has been re-named the "New Amalga Mine Project" in recognition of the gold mining heritage of the local project area. The historic Amalga Gold Camp located approximately four miles (6.5km) from the project site, produced tens of thousands of ounces of lode gold during the early 20th century. Today, little evidence remains from this once-bustling hub of mineral production, the site having been overtaken by the rapidly advancing temperate forest.

The Conceptual Mining Plan evaluates the development of a selective underground mining operation which would extract high-grade material with minimal dilution. Due to the project's location near tidewater and less than 4 miles (6.5km) from existing paved highway, the Company considers off-site processing to be the most favourable configuration and is investigating numerous business opportunities including strategic partnerships, potential use of third-party facilities around the Pacific Rim, and direct shipment to smelters in East Asia.

The Company's board of directors, management and its advisors assess that an offsite-processing configuration for the New Amalga Mine is the optimal development pathway, providing a number of potential benefits including:

  1. Elimination of the requirement to develop a tailings disposal facility near the mine. No tailings would be generated at the site.

  2. Elimination of the requirement for permanent waste rock storage facilities. All waste rock generated from mine access development would be returned to the underground workings for stope backfill.

  3. No use of gold processing reagents at the site.

  4. Dramatically reduced land usage and overall environmental footprint.

  5. Greatly simplified post-mining closure and reclamation.

  6. De-risking of the environmental review and permitting process.

  7. Minimization of project construction CAPEX.