GoviEx's Madaouela 1 Mining Permit revised to include an additional 23.84 Million Pounds of Measured and Indicated Mineral Resources

In This Article:

Vancouver, British Columbia--(Newsfile Corp. - September 23, 2019) - GoviEx Uranium Inc. (TSXV: GXU) (OTCQB: GVXXF) ("GoviEx"), is pleased to announce that further to GoviEx's news release of July 19, 2019, the Republic of Niger (the "State") has formally approved the revision to the shape of the Madaouela I Mining Permit that forms part of GoviEx's flagship Madaouela uranium project in Niger (the "Madaouela Project") to include the additional 5.96 million pounds (Mlb) U3O8 in the Measured and Indicated categories associated with the Miriam uranium deposit as well as 17.88 million pounds (Mlb) U3O8 in the Measured and Indicated categories associated Madaouela South North East ("MSNE") deposit, both previously situated within the Agaliouk exploration permit.1,2 In addition, the State has confirmed the environmental and social impact assessment certificate for the Madaouela I Mining Permit also covers both the Miriam and MNSE deposits.3 As this mineralization is not in a proven and/or probable mineral reserves category these mineral resources have not been included in the economic technical study included in the 2015 prefeasibility study.

"These 23.84 million pounds of measured and indicated mineral resources were discovered and delineated by GoviEx' geologic exploration team.1,2 As a result of this focused effort as well as GoviEx's continued social and environmental work and support and cooperation with the State, these resources are now included in the Madaouela 1 Mining Permit. We warmly welcome this significant milestone, as we advance the optimization work and the de-risking efforts of the targeted mineral resources contained within the Madaouela Project." said Chairman Govind Friedland.

Notes:

  1. An independent NI 43-101 technical report was prepared for the Madaouela Project in 2015 to a prefeasibility level of confidence. The report titled "An Updated Integrated Development Plan for the Madaouela Project, Niger" has an effective date of August 11, 2015, and a revision date of August 20, 2015, and is available at GoviEx's profile on SEDAR at www.sedar.com.

  1. See table below.

  1. GoviEx does not consider this to be a material change in relation to the issuer thereby requiring filing of an updated technical report.

Summary of the classified mineral resources in accordance with CIM guidelines for Madaouela (cut-Off: 0.4 kg/t eU) current as of the date of this news release1

Classification

Tons (Mt)

Grade (kg/t eU3O8)

eU3O8 (t)

eU3O8 (Mlb)

Marianne/Marilyn

Measured

2.14

1.79

3,835

8.45

Indicated

14.72

1.43

21,000

46.30

Inferred

5.04

1.17

5,910

13.02

Miriam

Measured

9.62

1.08

10,397

22.92

Indicated

2.68

0.79

2,112

4.66

Inferred

0.58

1.33

773

1.70

MSNE

Indicated

5.05

1.61

8,111

17.88

Inferred

0.10

1.34

131

0.29

Maryvonne

Indicated

1.23

1.79

2,195

4.84

Inferred

0.42

1.66

703

1.55

MSCE

Inferred

0.72

1.81

1,308

2.88

MSEE

Inferred

1.45

1.64

2,373

5.23

La Banane

Indicated

1.57

1.64

2,589

5.71

Inferred

1.15

1.18

1,358

2.99

Total Measured

11.76

1.21

14,232

31.37

Total Indicated

25.25

1.43

36,007

79.39

Total Inferred

9.46

1.33

12,556

27.66