Global Atomic Announces Q2 2024 Results

In This Article:

Dasa Uranium Project Remains on Schedule to Produce Yellowcake in Q1 2026

TORONTO, Aug. 12, 2024 /CNW/ - Global Atomic Corporation ("Global Atomic" or the "Company"), (TSX: GLO) (OTCQX: GLATF) (FRANKFURT: G12) announced today its operating and financial results for the quarter ended June 30, 2024.  For more detail, please refer to the Condensed Interim Consolidated Financial Statements and Management's Discussion and Analysis for the three and six months ended June 30, 2024, on the Company's website at www.globalatomiccorp.com.

Global Atomic - TSX30 - OTC (CNW Group/Global Atomic Corporation)
Global Atomic - TSX30 - OTC (CNW Group/Global Atomic Corporation)

Q2 2024 HIGHLIGHTS

Dasa Uranium Project – Mine Development

  • Ramp development has been underway since the Opening Blast Ceremony, November 5th, 2022, with over 1,235 meters completed as of the date hereof; and 7,000 tonnes of development ore now hauled to surface. Mine development is continuing with level development in the footwall and decline development.

  • Raise Boring is now underway for the Fresh Air Raise and Return Air Raise which will act as the main components of the mine's ventilation infrastructure.

  • As of the date hereof, the Dasa Mine, operated by SOMIDA and overseen by Global Atomic Corporation, has achieved 732 days without a Lost Time Injury ("LTI"), a testament to management's dedication to create a safe work environment and the team's success in implementing effective safety measures.

Dasa Uranium Project – Plant Construction

  • The Company began extensive earthworks in Q2 2024 to prepare the site for construction of the Dasa processing plant as well as expansion of the Daiy Camp to house employees and construction crews.

  • A 250-person housing facility has arrived on site. Civil works are underway for cement pads, water and sanitary facilities.

  • The Dasa Project Acid Plant fabrication has been completed and the plant is now being shipped to site. This will be the first major construction that will get underway once the shipment arrives at Dasa.

  • Our EPCM contractors have made significant progress to complete final engineering and order long lead items.

  • The procurement team is working to advance product specifications and select vendors for plant parts and equipment.

Turkish Zinc Joint Venture

  • In Q2 2024, the Turkish JV processed 19,162 tonnes of Electric Arc Furnace Dust ("EAFD").

  • Zinc contained in concentrate shipments totalled 7.4 million pounds and the average monthly LME zinc price was US$1.31/lb in Q2 2024.

  • The Company's share of the Turkish JV EBITDA was a gain of $2.8 million in Q2 2024 (a loss of $1.4 million in Q2 2023).

  • The cash balance of the Turkish JV was US$5.1 million at the end of Q2 2024.