Giyani Progresses to Production Ramp-Up at the Demonstration Plant

In This Article:

Giyani Metals Corp.
Giyani Metals Corp.

TORONTO, Jan. 31, 2025 (GLOBE NEWSWIRE) -- Giyani Metals Corp. (TSXV:EMM, GR:A2DUU8) ("Giyani" or the "Company"), developer of the K.Hill Battery-Grade Manganese Project in Botswana ("K.Hill" or “the Project”), is pleased to provide an update on the start of production at the Demonstration Plant (“Demo Plant”) in Johannesburg.

Highlights:

  • The Production ramp-up (C5 Commissioning) phase has commenced, and the team continues to work determinedly towards first production of battery-grade manganese (HPMSM). The Demo Plant materially advanced Hot Commissioning (C4 Commissioning) during January 2025. C4 and C5 commissioning naturally progress in parallel in the final stages of commissioning.

  • Demo Plant product samples are on track to be produced in Q1 2025 and then provided to potential off-takers to begin qualification trials as part of the offtake process, which will form an integral component of Project Financing.

  • The Demo Plant is designed to identify opportunities, improve the design, and significantly derisk the project as Giyani will better understand how the Commercial Plant (to be built in Botswana) will respond in advance of construction, commissioning, and ramp-up.

  • The Demo Plant also enables final optimisation of the engineering design and flowsheet in order to reduce operating costs and carbon profiles, in parallel with the Definitive Feasibility Study (“DFS”) which is underway and expected to be completed in 2025.

  • In addition to targeted operating cost reductions, Giyani announced last week the receipt of its Special Economic Zone (“SEZ”) licence for its Commercial Plant which is planned for construction adjacent to Giyani’s extensive, 100% owned manganese ore sources in Botswana.

  • The SEZ licence will directly positively impact the Company, as the SEZ Licence brings with it fiscal and non-fiscal benefits. Important to note is that the Company will benefit from 5% corporate tax rate for the first 10 years of production from its Commercial Plant, increasing to 10% thereafter, a considerable benefit which was not included in the 2023 PEA.

  • CEO Charles FitzRoy has also been in Johannesburg this week, seeing the Demo Plant progress ahead of our pre-Indaba investor site visit to the Demo Plant on February 1, 2025. The Giyani team are also attending the 121 conference and the Indaba conference in Cape Town next week, with a full schedule of off-taker, investor, and strategic meetings.

Charles FitzRoy, President and CEO of the Company, commented:

“Giyani’s Demo Plant is progressing to the production ramp-up commissioning phase , and the team continues to work determinedly towards first production of battery-grade manganese. We are targeting first production of HPMSM in Q1 2025. Our technical and operational teams are demonstrating excellent skill and resilience in navigating the usual late-stage commissioning challenges that occur when plants ramp-up toward production.