Generation Completes Optimization Work for the Marathon Project with Improved Mine Plan and Reduced Capex

In This Article:

Highlights:

  • Mine plan optimized with reduced strip ratio bringing additional 78k ounces of palladium, 34k ounces of Platinum and 2M lb of Copper in the first 3 years

  • Estimated $190M in additional payable revenues1 and operating cost benefits by the end of year 3 of operations

  • Initial Capital estimate reduced by $89M despite industry-wide inflationary cost pressures

  • Improved Project Economics with a 26% after-tax IRR and 2.1 year after-tax payback period1

TORONTO, November 20, 2024--(BUSINESS WIRE)--Generation Mining Limited (TSX:GENM, OTCQB: GENMF) ("Gen Mining" or the "Company") is pleased to provide an update on the project optimization work (the "Optimization Work") previously announced on June 6, 20242 on the Marathon Palladium-Copper Project (the "Marathon Project") in Northwestern Ontario. The Optimization Work focused on two key aspects: (1) optimization of the mine plan to maximize metal production and defer waste stripping in the early years of operations in order to improve early cash flows and reduce the payback period ("Mine Plan Optimization"); and (2) review and optimization of the plant design and layout, including sizing of key equipment, plant footprint and foundations, in order to reduce the initial Project capital costs ("Initial Capital Optimization").

Jamie Levy, President and CEO, commenting on the Optimization Work, remarks:

"The optimized mine plan is a notable improvement to the existing plan, with $190 million in additional payable metal revenues1 and savings from a reduced strip ratio during the initial 3-years of mine operations.

The other meaningful improvement to the project is the optimized plant design and ancillary changes recommended by Ausenco, which represent a net savings in total project capital costs of over $89 million, after taking into account the impact of inflation on certain construction materials and equipment, and other design change escalations since the end of 2022.

This optimization work by Ausenco and our team represents a meaningful improvement to the financeability, constructability and economics of our project following several years of significant inflation in many input costs, and validates the continued robustness of the Marathon Project."

The Mine Plan Optimization was carried out by the Company and the Initial Capital Optimization was performed by the Company in collaboration with Ausenco Engineering Canada ULC ("Ausenco"). All amounts are reported in Canadian dollars unless otherwise noted herein.