Forge Resources Corp Announces Significant Progress of Portal Construction at Fully Permitted La Estrella Coal Mine, Colombia and Hiring of Mining Engineer Emilio Gene and Hiring of Marketing Firms

In This Article:

Vancouver, British Columbia--(Newsfile Corp. - January 24, 2025) - Forge Resources Corp. (CSE: FRG) (OTCQB: FRGGF) (FSE: 5YZ) ("FRG" or the "Company") is pleased to announce significant progress at its fully permitted La Estrella Coal Mine in Santander, Colombia, with the main portal construction nearing 90% completion.

La Estrella Portal Progress

The portal was designed and built by AB INGENIERÍA Y CONSTRUCCIÓN SAS. The new portal will provide access to previously untapped coal reserves and is the first step in securing the 20,000 Metric tonne bulk sample of metallurgical and thermal coal. This significant development marks a major milestone in the company's ongoing commitment to enhancing operational efficiency, safety, and ensuring sustainable resource extraction.

The portal incorporates sustainable practices designed to enhance operational efficiency while minimizing environmental impact. Key features include advanced ventilation systems, reinforced structural supports, and state-of-the-art safety measures to ensure the protection of both workers and the surrounding environment.

Figure 1 - Portal Construction Progress as of Jan 23, 2024

To view an enhanced version of this graphic, please visit:
https:/https://finance.yahoo.com/images.newsfilecorp.com/files/8680/238447_5296a7d394a5b9b7_001full.jpg

In addition to the portal construction, significant progress has been achieved on slope stabilization with crews actively working on terracing the adjacent slope to enhance site stability. These measures underscore Aion Mining's commitment to ensuring a safe and secure operational environment as development activities intensify.

Cole McClay, COO of Forge Resources, states: "Completion of the portal is the foundation for the commencement of decline development, bringing us one step closer to accessing the coal seams for our bulk sample. Our team's dedication and focus on safety and efficiency have been instrumental in reaching this stage, and we remain committed to delivering on our operational goals as we advance toward full project realization."

Figure 2 - Portal Construction Progress as of Jan 23, 2024

To view an enhanced version of this graphic, please visit:
https:/https://finance.yahoo.com/images.newsfilecorp.com/files/8680/238447_5296a7d394a5b9b7_002full.jpg

Emilio Gene Appointed La Estrella Project Manager

Forge Resources is pleased to introduce Mr. Emilio Gene as Project Manager for the Colombian coal project. A seasoned Mining Engineer with 16 years of expertise in underground coal mining, Mr. Gene brings extensive experience in project management, mineral extraction, and safety. His distinguished career includes pivotal roles such as Chief of Mining Operations and Safety Supervisor at Industria Carbonífera de Samacá. Mr. Gene's impressive credentials include a Mining Engineering degree from Francisco de Paula Santander University and a Degree in Business Management from the Pedagogical and Technological University of Colombia.