Foran Showcases Construction Progress at McIlvenna Bay

In This Article:

VANCOUVER, BC, Dec. 3, 2024 /CNW/ - Foran Mining Corporation (TSX: FOM) (OTCQX: FMCXF) ("Foran" or the "Company") is pleased to share a progress update on the construction of its 100% owned McIlvenna Bay project in Saskatchewan, Canada, alongside new photos showcasing ongoing development. The images offer a detailed look at key milestones reached during October 2024 and can be viewed in the image gallery on our website at www.foranmining.com/news-media.

McIlvenna Bay Site - Looking North (CNW Group/Foran Mining Corporation)
McIlvenna Bay Site - Looking North (CNW Group/Foran Mining Corporation)

Key October 2024 Achievements:

  • Progressed foundation formwork and rebar installation for the process plant building, including concrete works in the floatation areas and concentrate loadout.

  • Installed the semi-autogenous grinding ("SAG") mill shell, heads, and trunnions, and mounted the ball mill shell.

  • Some structural steel for the process plant has been delivered to site, with pre-assembly and staging underway.

  • Completed concrete work for the surface maintenance shop heavy equipment bays, erected structural steel, and installed the crane bridge.

  • Finalized under-pad earthworks for the waste rock and ore pad expansion and began placing the liner and topsoil layer.

  • Advanced drilling and blasting of bedrock at the contact water pond.

  • Completed the concrete pad for the temporary underground equipment maintenance shop.

  • Nearly completed the treated water discharge pipeline corridor to Winn Bay and began fusing pipe.

  • Substantially completed the new security gatehouse and advanced work on the main parking lot area and helipad.

  • Completed approximately 343 metres of underground lateral development in October 2024, the highest monthly advance for the project to date. The main decline is now nearing the 150m level.

  • Progressed with the excavation of the main ventilation fresh air raise, with focus on permanently sealing the sandstone layer from water ingress into the raise.

  • Construction of concrete floor for underground BEV equipment charging bay on 60m level.

  • Continued aggregate material crushing operations.

As the Company continues to advance the project, Foran remains committed to the safe and timely development of McIlvenna Bay. A detailed update on construction progress will be provided following the quarter ending December 31, 2024.

Qualified Person

Mr. Samuele Renelli, P. Eng., Vice President, Technical Services for Foran, is the Qualified Person for all technical information in this news release and has reviewed, verified and approved the technical information in this news release.

About Foran Mining

Foran Mining is a copper-zinc-gold-silver exploration and development company, committed to supporting a greener future and empowering communities while creating value for our stakeholders.  The McIlvenna Bay Project is located entirely within the documented traditional territory of the Peter Ballantyne Cree Nation, comprises the infrastructure and works related to development and advanced exploration activities of the Company, and hosts the McIlvenna Bay Deposit and Tesla Zone. The Company also owns the Bigstone Deposit, a resource-development stage deposit located 25 km southwest of the McIlvenna Bay Property.