Erdene Announces Year-End Results and Provides Bayan Khundii Project Update

In This Article:

Erdene Resource Development Corporation
Erdene Resource Development Corporation

HALIFAX, Nova Scotia, March 25, 2025 (GLOBE NEWSWIRE) -- Erdene Resource Development Corp. (TSX:ERD; MSE:ERDN) ("Erdene" or the "Company") is pleased to announce operating and financial results for the year ended December 31, 2024, and to provide an update on progress at the Bayan Khundii Gold Project, being developed with Mongolian Mining Corporation (“MMC”). This release should be read in conjunction with the Company’s 2024 Financial Statements and MD&A, available on the Company’s website and SEDAR+.

Peter Akerley, Erdene’s President and CEO stated, “The past year was a period of significant progress for Erdene with the close of our Strategic Alliance with MMC, Mongolia’s leading publicly traded mining company, the commencement of construction at the Bayan Khundii gold project and continued exploration success across the Khundii Minerals District.”

He continued, “The Bayan Khundii gold mine is one of the highest grade, open-pit gold mines under development globally and will be Mongolia’s largest primary gold producer when it reaches full production. As of today, construction progress has exceeded 80% with most facilities scheduled for completion in Q1 and early Q2 2025. Three key facilities have been commissioned and process plant commissioning is expected to commence in May 2025, with first gold production scheduled in Q3 2025.”

Mr. Akerley concluded, “Expansion drilling during 2024 returned the highest grades to date adjacent to the planned Bayan Khundii open-pit, demonstrating strong growth potential. Additionally, ore-control drilling in late 2024 returned very positive results, confirming the high-grade nature of the Bayan Khundii deposit, and in some cases expanding mineralization. These results will be incorporated into an updated Bayan Khundii mine plan in the coming months.”

2024 Highlights and Significant Subsequent Events:

Images – clockwise from top left: Bayan Khundii Construction Site, Process Plant, Accommodation Village, and Crushing and Conveyor System, March 2025.
Images – clockwise from top left: Bayan Khundii Construction Site, Process Plant, Accommodation Village, and Crushing and Conveyor System, March 2025.

Images – clockwise from top left: Bayan Khundii Construction Site, Process Plant, Accommodation Village, and Crushing and Conveyor System, March 2025.

Bayan Khundii Gold Project

  • Announced formal construction decision for Bayan Khundii on January 15, 2024

    • Awarded the Project’s Engineering, Procurement and Construction (“EPC”) services contract to MCS Property LLC (“MCSP”), a leading Mongolian construction firm

    • Entered a power purchase agreement (“PPA”) for the construction of a 240 km overhead transmission line with MCS International LLC (“MCSI”), one of Mongolia’s leading private energy companies

  • Achieved 66% construction progress by December 31, 2024

    • Incurred US$83 million of expenditures to the end of Q4 2024

    • EM management estimates capital expenditures may increase by ~ 15% from the initial capital budget of US$100M due to inflation, the impact of weather and logistical delays and scope changes; however, no further equity funding is expected from Erdene or MMC for BK

    • Process plant, the critical path facility, was 67% complete at year end, with concrete and structural works substantially completed and all major equipment in place

    • Construction progress for non-process buildings was 60%, infrastructure facilities were 80%, and power supply was 52%, largely consistent with schedule

    • Commissioning of the integrated mineral waste facility was completed in Q4 2024 with the balance of the facilities planned progressively throughout Q1 and Q2 2025

    • Construction expected to be largely complete in May 2025 to allow commissioning of processing facilities in Q2 2025 and first gold production in Q3 2025

  • Delivered on community development and local employment stakeholder programs

    • Local Cooperation Agreement for 2024 implemented supporting local development

    • Recruitment and training of Bayan Khundii mine workforce continued with eighth cohort of local residents selected for equipment operator training at MMC’s UHG mine, for a cumulative total of 164 people undertaking the training

    • Company supported installation and improvement of three rural water wells to increase water availability for residents