Endeavour Announces Wet Commissioning is Underway at Sabodala-Massawa BIOX Expansion

In This Article:

Endeavour Mining PLC
Endeavour Mining PLC

First gold expected in May · Project on schedule and on budget with no LTIs · 91% project completion

      ENDEAVOUR ANNOUNCES WET COMMISSIONING IS UNDERWAY AT SABODALA-MASSAWA BIOX EXPANSION

First gold expected in early May · Project on schedule and on budget with no LTIs · 91% project completion


HIGHLIGHTS:

  • Over 3 million man hours have been completed with zero lost-time injuries

  • Wet commissioning is underway with overall construction activities 91% complete

  • Expansion project on budget and on schedule with the first gold pour expected in early May

  • Sabodala-Massawa is expected to produce between 360-400koz at a sector leading AISC of between $750-850/oz in FY-2024

  • Sabodala-Massawa is the largest exploration focus this year with a guided spend of $21 million

Dakar, 27 February 2024 – Endeavour Mining plc (LSE:EDV, TSX:EDV, OTCQX:EDVMF) (“Endeavour”, the “Group” or the “Company”) is pleased to announce that wet commissioning activities are now underway at the Sabodala-Massawa Expansion project (“BIOX® Expansion”) in Senegal. The BIOX® Expansion project is on budget, with construction now 91% complete, and the first gold pour is expected on schedule, in May.

Ian Cockerill, CEO, commented: “We are extremely pleased with our progress as we start wet commissioning at the BIOX® Expansion project. Importantly, we have achieved this milestone with no lost-time injuries having worked more than 3 million man hours, which is a testament to the strong safety culture that is a hallmark of our in-house construction teams.

At completion, Sabodala-Massawa will become a true top tier asset with 2024 production of up to 400koz at an industry leading AISC of less than $850/oz, with costs expected to improve further in the coming years, embedding the mine firmly in the lowest cost quartile.

This year, Endeavour is well positioned to transition from a phase of investment in organic growth, to a more cash flow generative phase in the second half of the year. This inflection point will allow us to focus our efforts on increasing our shareholder returns while de-levering our balance sheet, as we continue to execute on our strategy.”

Wet commissioning of the BIOX® Expansion was delivered in less than 23 months after construction was launched in April 2022. During construction activities, up to 1,300 employees and contractors were on site, 82% of whom were Senegalese nationals, successfully completing over three million man-hours with zero lost time injuries.

The addition of the 1.2Mtpa BIOX® Expansion, with an initial capital cost of $290 million, is expected to add 194koz per annum of incremental production over the first five years, lifting Sabodala-Massawa to top-tier status with expected production of 360-400koz at an AISC of between $750-850/oz in FY-2024, increasing to above 400koz from 2025.