DYLLF: The Final Investment Decision (FID) for the Tumas Project will now be made in March 2025. An upgraded Ore Reserve Estimate on the Tumas Project, which now supports a LOM of 30 years, requires additional work to make a prudent FID.

In This Article:

By Steven Ralston, CFA

OTCQX:DYLLF | ASX:DYL

READ THE FULL DYLLF RESEARCH REPORT

Deep Yellow (OTCQX:DYLLF) (ASX:DYL) is on the threshold of entering the mine construction phase as management awaits the receipt of costings and quotes for both equipment and construction as well as the results of additional optimization studies. The Final Investment Decision (FID) for the Tumas Project has been deferred until early March 2025. The Board is also taking a very disciplined approach and believes that the start-up of a greenfield uranium project at the current uranium price in the low $70 range would not in the best interest of shareholders since that price level does not reflect the looming critical supply shortage.

The significant equity financing in May 2024 provided the necessary capital to continue moving forward with the Tumas Project. Furthermore, management is progressing toward securing debt financing in order to ensure funding will be available for construction costs when once the FID is made to proceed. Potential lenders have indicated a keen interest in supporting the project.

Management continues to move forward in readying Tumas for the mine construction phase.

In mid-August 2024, three RC rigs commenced a 12.5m x 12.5m spacing grade-control drilling program at Tumas 3 for the purpose of creating a detailed mining plan. By early December 2024, approximately 60% of the program had been completed, specifically 1,667 holes (23,921m) that targeted the planned small open pit areas near the proposed plant site. The program also includes preparation work on tailings sites and is expected to be completed in late-March.

Offers for volume and price for both water and power have been received (from NamWater and NamPower, respectively). The company has accepted both offers and the contracts being finalized for execution.

The company remains well funded with a cash balance of AUD$238.4 million as of December 31, 2024.

Deep Yellow Ltd remains on track to become a low-cost, Tier I uranium producer, which management defines as a multi-project producer of uranium with the capacity to deliver 5-10 million lbs. of uranium annually.

RECENT EVENTS

Ore Reserve Estimate (ORE) for the Tumas Project Increases 18%

On December 18, 2024, Deep Yellow announced an 18% increase of Ore Reserve Estimate (ORE) for the Tumas Project on ML237. The updated ORE Increased from 67.3 Mlb U3O8 at 345 ppm (150 ppm cut-off) to 79.3 Mlb U308 at 298 ppm (100 ppm cut-off). Management continues to work towards a Final Investment Decision (FID).

When the upgrade in Ore Reserves is incorporated into an updated DFS, it is expected that the NPV and the IRR of the Tumas Project will increase and also the LOM will exceed 30 years.