Denison Reports Financial and Operational Results for 2024 Highlighted by Significant Advancement of the Phoenix Project

In This Article:

Denison 70 Logo (CNW Group/Denison Mines Corp.)
Denison 70 Logo (CNW Group/Denison Mines Corp.)

TORONTO, March 13, 2025 /CNW/ - Denison Mines Corp. ('Denison' or the 'Company') (TSX: DML) (NYSE American: DNN) today filed its Audited Consolidated Financial Statements and Management's Discussion & Analysis ('MD&A') for the year ended December 31, 2024. Both documents will be available on the Company's website (at www.denisonmines.com), SEDAR+ (at www.sedarplus.ca) and EDGAR (at www.sec.gov/edgar.shtml). The highlights provided below are derived from these documents and should be read in conjunction with them. All amounts in this release are in Canadian dollars unless otherwise stated. View PDF version

David Cates, President and CEO of Denison commented, "The Denison team was active across all aspects of our business in 2024, and owing to several important achievements during the year, we are well-positioned to execute on our objective to build and operate the next new large-scale uranium mine in northern Saskatchewan. 

We significantly advanced the regulatory approvals process for our Phoenix In-Situ Recovery ('ISR') project, culminating in the Canadian Nuclear Safety Commission ('CNSC') scheduling a two-part public hearing ('Hearing') for the project to occur in late 2025, which could allow for project approvals and start of construction in early 2026 and for first production to be achieved, in line with our previous guidance, by the first half of 2028. 

In anticipation of this timeline, our operations team has progressed our detailed design engineering efforts for Phoenix – having achieved approximately 65% completion of total engineering by the end of 2024.  With clarity on the Hearing schedule, our operations team can now finalize our construction plans with greater precision and with an objective to be ready to commence construction shortly after receiving the necessary regulatory approvals. 

We also announced the signing of a Mutual Benefits Agreement with Kineepik Métis Local #9, a Community Benefit Agreement with the northern Village of Pinehouse Lake, and a Sustainable Communities Investment Agreement with multiple northern municipalities.  With each of these agreements, Denison has obtained further consent and support for mine development and operations on the Wheeler River property. 

Beyond Wheeler River, there were notable developments from our McClean Lake and Midwest joint ventures with Orano Canada Inc. ('Orano Canada') and our exploration project portfolio.  At McClean Lake, development work progressed at the McClean North deposit in preparation for the restart of mining in 2025, which will use the joint venture's patented Surface Access Borehole Resource Extraction ('SABRE') mining method.  At Midwest, an inaugural ISR field test program was completed, which validated key assumptions and advanced our evaluation of the potential use of ISR mining at Midwest.  In an effort to amplify our exposure to exploration discovery, we also entered into agreements with each of Foremost Clean Energy (Nasdaq: FMST) and Cosa Resources (TSX-V: COSA) to collaborate on the exploration of several of Denison's non-core exploration properties. 