Cornish Metals Provides Update for the South Crofty Tin Project

In This Article:

Cornish Metals Inc.
Cornish Metals Inc.

First pump installation underway in New Cooks Kitchen shaft
Substantial amount of Feasibility Study completed
New Mineral Resource Estimate planned for Q3, 2023

VANCOUVER, British Columbia, June 14, 2023 (GLOBE NEWSWIRE) -- Cornish Metals Inc. (TSX-V/AIM: CUSN) (“Cornish Metals” or the “Company”) is pleased to provide an update on progress at the South Crofty Tin Project (“South Crofty” or the “Project”), located in Cornwall, SW England.

Richard Williams, CEO and Director, stated “Activities at South Crofty continue at a good pace with the commencement of dewatering on-track for later this summer. Good progress is also being made with many aspects of the Feasibility Study to examining the re-opening of South Crofty. Initial results are very encouraging. The mine site team have also reached another important milestone with the installation of the first submersible pump into NCK shaft now underway.”

Submersible Pump Installation

The first submersible pump has been suspended in New Cooks Kitchen (“NCK”) shaft:

  • This pump is the first of two submersible pumps to be installed in NCK shaft for Stage 1 of the two-stage mine dewatering programme;

  • The pumps are specialist high-head 950 kW vertical submersible pumps manufactured by KSB in Germany, controlled by variable speed drives to enable the 25,000 cubic metres (m3) per day pumping rate to the Mine Water Treatment Plant (“MWTP”) to be maintained as the water level drops and the pumping head increases;

  • The pumps will be lowered to immediately below the 195 fathom level (360 metres below surface) suspended from one hundred and twenty x 3-metre long pipes that will form the temporary rising main;

  • When the water level reaches 195 fathom level, (360m below surface) a permanent set of pumps will be installed and the submersible pumps will be lowered to the 400 (approximately 700m below surface) fathom level for Stage 2 of the dewatering programme;

  • Installation of the second pump is expected to commence before the end of June;

  • See photos 1, 2, and 3 here.

Feasibility Study

Work continues on the Feasibility Study with highlights summarised below:

  • The metallurgical testwork programme is well underway with Wardell Armstrong International, physical competency, characterisation and gravity response testwork has been completed on No.4, No.8 and Roskear Lodes, with mineralogy completed by Petrolab Ltd. Early gravity response results have been very good and are in line with previous operational results.

  • The first bulk composite sample of the metallurgical testwork programme has arrived in Germany for XRT ore sorter testing at TOMRA Sorting GmbH.

  • Fairport Engineering, who completed an initial conceptual study of the processing plant design, layout and cost in Q1 2023, have nearly completed the second optimisation phase, prior to the feasibility level design, which will incorporate further results of the metallurgical testwork programme. The final plant design will incorporate potential future throughput expansions;

  • Site investigation for the process plant footprint has been completed by AGS Ground Solutions;

  • Numerical modelling of the proposed underground mining methods and stope designs has been completed by MiningOne. Results confirm the historical operating data and that the ground conditions and excavation stability are expected to be very good.

  • Geotechnical televiewing has been completed on the majority of mining areas by RobertsonGeo, validating previous known structural data. Core samples have been taken for laboratory testing.

  • Paterson & Cooke UK has started concept engineering on paste backfill options and physical testing, preliminary results show samples gain sufficient strength at target densities.

  • Entech Mining is working with RSV Group to provide method, costing and schedule for refurbishment and recommissioning of NCK and Roskear shafts.

  • Piteau Associates has been engaged for the Hydrogeological works for the Feasibility Study.