CleanTech Lithium PLC Announces PFS Plant Location Study Results

In This Article:

PFS Plant Location Study Results in Decision to Locate Carbonation Plant in Mining Centre of Copiapó

JERSEY / ACCESSWIRE / July 2, 2024 / CleanTech Lithium PLC (AIM:CTL)(Frankfurt:T2N)(OTCQX:CTLHF), an exploration and development company advancing sustainable lithium projects in Chile, announces the results of a plant location study completed as part of the ongoing pre-feasibility study (PFS) for the Laguna Verde Project, which is due to complete later this year. The PFS is being led by Worley, a global professional services company of energy, chemicals and resources experts, from its Santiago office which has high-level experience in the lithium sector. Xi´an Lanshen New Material Technology Company ("Lanshen") has been selected to provide the lithium processing plant design and equipment, and Worley to design the balance of plant and infrastructure.

Highlights:

  • A plant location study was completed by Worley, which evaluated the optimal plant location configuration for the Laguna Verde project, based on a capacity of 20,000 tonnes per annum of battery grade lithium carbonate equivalent (LCE)

  • This provided a trade-off analysis between locating the entire plant at Laguna Verde versus splitting plant facilities between Laguna Verde and the nearby mining centre of Copiapó

  • The option of locating the DLE plant and eluate concentration stages at the Laguna Verde site, and the carbonation plant at Copiapó is highly favourable, resulting in the decision to proceed with this option

  • A concentrated eluate with 6% lithium, the maximum concentration before lithium salts begin to precipitate, will be transported to Copiapó for impurity removal and carbonation stages

  • This configuration results in a minor increase in volumes transported while taking advantage of Copiapó's well-developed infrastructure and better access to a skilled workforce

  • According to the Lanshen plant design, approximately 70% of the operational workforce will be employed at the carbonation plant, locating it in Copiapó provides major advantages in hiring a local work force including diversity outcomes such as greater female participation, while contributing to the local economy

  • The footprint at the project site, which is at 4300m above sea level, will be greatly reduced, from power supply, storage, camp and plant facilities, construction phase impacts, and environmental impacts

  • The carbonation plant in Copiapó would eventually be expanded to also treat concentrated eluate from the Viento Andino project

  • The PFS, now due for completion before the end of Q4 this year, will include updated capex and opex estimates and will further determine the optimal production development strategy