Cheniere Begins LNG Production at Corpus Christi Stage 3 Project

In This Article:

Cheniere Energy, Inc. LNG, a leading player in the liquefied natural gas (“LNG”) industry, has announced a significant achievement in its Corpus Christi Stage 3 Liquefaction Project (CCL Stage 3). The project has reached a milestone with the first production of LNG from Train 1, marking the commencement of a new phase in the company's expansion efforts. Although the commissioning process is still in progress, Cheniere expects Train 1 to be substantially completed by the end of the first quarter of 2025, which is more than six months ahead of schedule.

 

LNG’s CCL Stage 3: Expanding Production Capacity

The CCL Stage 3 project is an integral component of Cheniere's strategy to expand its liquefaction capacity and strengthen the company’s position in the global LNG market. The project consists of seven midscale LNG trains, designed to enhance the production capacity of the Corpus Christi Liquefaction facility in Texas. Once completed, the project will increase the facility's total production capacity to more than 25 million tons per annum (mtpa) of LNG.

 

Progress and Timeline for Completion

As of Nov. 30, 2024, the overall project completion was 75.9%, with substantial progress across various phases of the project. The engineering phase was nearly finished, with 96.8% of the work completed. Procurement efforts were also nearing completion, with 97.2% of the necessary materials and equipment secured. Subcontract work was 87.7% complete, and construction, though behind in comparison to other areas, had reached 39.2% completion.

The oil and gas storage and transportation company issued the full notice to proceed to Bechtel Energy, Inc., the project’s primary contractor, in June 2022. Since then, Bechtel has worked diligently to advance the project and Train 1's successful LNG production marks a major step forward. After substantial completion of Train 1, Bechtel will transfer care, custody and control of the completed train to Cheniere, marking the official handover of the unit for operation.

 

Role of Bechtel in the CCL Stage 3 Project

Bechtel Energy plays a crucial role in the execution of the CCL Stage 3 project. As the main contractor, Bechtel is responsible for overseeing the construction, engineering and procurement aspects of the project. The company's expertise in large-scale energy infrastructure projects has been instrumental in advancing the development of the seven midscale trains. This work is expected to help Cheniere meet the increasing demand for LNG in domestic and international markets.