Candente Copper Provides Update

VANCOUVER, BRITISH COLUMBIA--(Marketwired - Jan 8, 2015) - Candente Copper Corp. (DNT.TO)(DNT.TO)(OTC PINK:CCOXF) ("Candente Copper" and/or the "Company" ) is pleased to provide the following Corporate and Project updates.

Further to appointing Endeavour Financial Limited (Cayman) as financial advisor for funding the Cañariaco Copper project, the Company has received Expressions of Interest in different forms of funding for the project. The Company is interested in forms that include but are not limited to: concentrate off-take, royalties, streaming, loans and joint venture agreements. The Company is furthering discussions with the parties expressing interest with the goal to obtain long term funding for the advancement of the Cañariaco project.

Feasibility Study Update for the Cañariaco Norte Project

The Feasibility Study of the Cañariaco Norte Project was initiated in April 2011 and although well advanced was put on hold in mid 2013 due to the deterioration in the investment climate for small cap mining exploration companies. The Feasibility Study is being conducted by Amec Foster Wheeler and supported by Knight Piesold Consultants, both of Vancouver. The Environmental Impact Assessment is being performed by AMEC (Peru) SA.

Overall, the Feasibility Study is approximately 50% complete. Activities completed to date include all resource drilling and resource estimation, metallurgical drilling, site layout, infrastructure and ancillary facilities design, and access road alignment. The process plant (grinding and flotation) layout is approximately 80% complete and will be finalized upon completion of metallurgical testwork. Geotechnical drilling for the pit design is 50% complete and approximately 80% of the field work for the Environmental and Social Impact Assessment study has been completed.

Additional metallurgical testwork is required to finalize design criteria for the cleaner flotation circuit and concentrate roasting processes. Limited geotechnical drilling is required to provide information to finalize the design criteria for the open pit wall slope and mine plan plus additional geotechnical assessment for facility foundation design and water management.

The Feasibility Study scope of development is based on the Prefeasibility Study Progress Report ("PFSPR") completed in March 2011, however the Feasibility Study incorporates several key modifications as identified below:

Process Design

The daily processing rate has been increased from 95,000 to 110,000 tonnes per day with a corresponding increase in annual copper production. The increase is achieved by utilizing a 40 foot diameter SAG mill in place of the 38 foot SAG mill as specified in the PFSPR, increasing the size of the ball mills and adding pebble crushers to the primary grinding circuit. Importantly, even with the throughput increase the crushing and grinding circuit will retain a single line configuration with one primary crusher, one SAG mill and two ball mills.