Bunker Hill Provides November 2023 Restart Project Update

In This Article:

Bunker Hill Mining Corp.
Bunker Hill Mining Corp.

Live 6ix Summit by Video from Bunker Hill Site on Tuesday 28 Nov @ 0900 PST/1200 EST

Compressor Building

Compressor Building
Compressor Building

Shop Facility in construction

Shop Facility in construction
Shop Facility in construction

Atlas Copco Mucker

Atlas Copco Mucker
Atlas Copco Mucker

Tails Filtration 3d-Rendering (1)

showing location, coincident with the main processing facility in the Bunker Hill Yard
showing location, coincident with the main processing facility in the Bunker Hill Yard

Tails Filtration 3d-Rendering (2)

showing location, coincident with the main processing facility in the Bunker Hill Yard
showing location, coincident with the main processing facility in the Bunker Hill Yard

PROJECT ADVANCING ON TIME AND BUDGET:

  • People:

    • Site team augmented with Chief Geologist and Site Controller joining team

    • New CFO, Gerbrand Van Heerden in role

  • Mining:

    • Underground Compressor installed in compressor building

    • Sprung shop structure constructed in Wardner Operating Yard

    • Procurement of Atlas Copco Mucker

  • Processing:

    • Tailings Facility and Paste Backfill Plant advanced in partnership with Tierra Group & Ausenco

    • Site Layout finalized and procurement process initiated for Paste and Tails management systems

NEXT STEPS

  • Commissioning of compressor, power, and UG Maintenance Shop

  • Geotechnical stabilization work for Process Plant

TORONTO, Nov. 22, 2023 (GLOBE NEWSWIRE) -- Bunker Hill Mining Corp. (the “Company”) (TSXV: BNKR) (OTCQB: BHILL) is pleased to provide an update on restart project activities during Q4 of 2023.

Sam Ash, CEO, said: “October marked another productive month at Bunker Hill that saw the team make significant advancements towards an on time and budget restart. Upon completion of the portal enlargement the underground team made great progress with the installation of the UG compressor, acquisition of an additional loader and construction of additional shop space at Wardner.” Particularly exciting is the incorporation ‘in house’ of the truly excellent and local CMC Mining Contractor and their equipment into the Bunker Hill Corporation.

A FIT FOR PURPOSE BASE FOR MINING OPERATIONS

Compressor Building
Compressor Building
Shop Facility in construction
Shop Facility in construction
Atlas Copco Mucker
Atlas Copco Mucker


Compressor Building

Shop Facility in construction

Atlas Copco Mucker


Additional activity in support of mining operations during this period included the following; Installation of new compressor into permanent building, Construction of shop facility, and the acquisition of an Atlas Copco mucker.

PROCESSING AND TAILINGS FACILITIES

Progress continues advancing the process plant, with engineering 95% complete including the finalization of the deep pier geotechnical stabilization plans. Refurbishment work is well underway on the many Pend Oreille process plant components in the onsite refurbishment shop under the direction of our new Maintenance Planner.

Engineering work on the tails filtration and paste plant are advancing on plan with initial 3d renderings now complete, showing their location within the Bunker Hill Yard.

Tails Filtration 3d-Rendering (1)
Tails Filtration 3d-Rendering (1)
Tails Filtration 3d-Rendering (2)
Tails Filtration 3d-Rendering (2)

Tails Filtration 3d-Rendering – showing location, coincident with the main processing facility in the Bunker Hill Yard


RECRUITING AND TEAM DEVELOPMENT