Bayhorse Receives Excellent Silver Assays for Silver Rich Bayhorse Silver Mine, Oregon, USA

In This Article:

Vancouver, British Columbia--(Newsfile Corp. - November 3, 2021) - Bayhorse Silver Inc (TSXV: BHS) ("Bayhorse" or the "Company") has received excellent assay results from recent underground drilling at its silver rich, Bayhorse Silver Mine, Oregon, USA.

The highest grade interval was 2,180g/t (63.65 oz/t) over 0.6m (2 ft.) in Hole BHDD008, a 24.5 m (80 ft) underground hole, which intersected a 3.66 meter (12 feet) interval from 17 m to 20.7 m (56 ft to 68 ft) assaying a weighted average of 844 g/t (24.65 oz/t).

The full results are tabulated below.

Sample ID

Hole ID

From ft

To ft

Au (ppm)

Ag (Tr. Oz/tn)

Cu %

Pb%

Sb

Zn

658145

21BHDD-008

40

45

<0.05

<0.05

<0.05

<0.05

<0.05

0.47

658146

21BHDD-008

45

48

<0.05

<0.05

<0.05

<0.05

<0.05

0.63

658147

21BHDD-008

48

51

<0.05

<0.05

<0.05

<0.05

<0.05

0.62

658148

21BHDD-008

51

54

<0.05

<0.05

<0.05

<0.05

<0.05

0.45

658149

21BHDD-008

54

56

<0.05

<0.05

<0.05

<0.05

<0.05

0.5

658151

21BHDD-008

56

58

<0.05

28.82

<0.05

<0.05

<0.05

0.85

658152

21BHDD-008

58

60

<0.05

63.65

<0.05

<0.05

<0.05

1.95

658153

21BHDD-008

60

62

<0.05

36.06

<0.05

<0.05

<0.05

2.59

658154

21BHDD-008

62

64

<0.05

8.50

<0.05

<0.05

<0.05

3.48

658155

21BHDD-008

64

66

<0.05

4.96

<0.05

<0.05

<0.05

2.05

658156

21BHDD-008

66

68

<0.05

5.96

<0.05

<0.05

<0.05

2.45

658157

21BHDD-008

68

74

<0.05

<0.05

<0.05

<0.05

<0.05

0.11

658158

21BHDD-008

74

75

<0.05

<0.05

<0.05

<0.05

<0.05

0.08

658159

21BHDD-008

75

79

<0.05

<0.05

<0.05

<0.05

<0.05

0.04

658161

21BHDD-008

79

80

<0.05

<0.05

<0.05

<0.05

<0.05

0.07

True width yet to be determined

BHDDH008 was drilled at the main haulageway intersection and intercepted stockwork mineralization with a weighted average of 844.5 g/t (24.65 oz/t).

The westerly trending Bayhorse mineralized zone is open to the west, averages 25 feet in thickness, and is up to 200 feet in width. It rises to the North of the main haulageway and dips to the south. The Company is currently conducting drilling operations in a zone 300 meters (1,000 ft) to 450 meters (1,500 ft) west of the Mine Portal.

Underground drilling operations proceed as underground drifting installs additional drill stations. Due to the shortage of experienced underground drillers, trained to Mine Safety and Health Administration (MSHA) requirements, the Company has been training its own underground drilling crews. Further drill results are pending and will be released when received.

Bayhorse CEO Graeme O'Neill comments, "Despite the unprecedented challenges posed this past year through Covid-related issues, the Company has steadily advanced on a number of fronts to measure, develop, and recover silver from the Bayhorse." He further comments that, "The new mill building has been erected with mill equipment currently being installed, with completion projected for renewed operation by early December."