Aura Minerals Announces Second Quarter 2022 Production Results, Exploration Updates and Status on the Almas Project Construction

Aura Minerals Inc
Aura Minerals Inc

Consolidated GEO Production per Quarter and LTM

(000 GEO, current prices as reported)
(000 GEO, current prices as reported)

ROAD TOWN, British Virgin Islands, July 11, 2022 (GLOBE NEWSWIRE) -- Aura Minerals Inc. (TSX: ORA) (B3: AURA33) (“Aura” or the “Company”) is pleased to announce production results from the Company’s three producing operations for the second quarter of 2022 and an update on exploration activities across its portfolio. Total production reached 55,645 gold equivalent ounces (“GEO”)1 during Q2 2022.

Highlights

  • Total production decreased 7% compared to the second quarter 2021 (59,834 GEO) primarily due to temporary lower recoveries at San Andres and increased processing of stockpiles at EPP Mine, consistent with management’s strategy to optimize cash flows.

  • Aranzazu Mine continued to achieve strong processing rates, with a maximum processing capacity slightly above 100,000 tons per month.

  • Production is expected to improve in the coming quarters, particularly at San Andres and EPP as higher-grade zones are accessed.

  • Robust infill and expansion drilling continued across the Company’s portfolio, including at Matupá where the Company intersected 80 meters @ 3.89 g/t Au and 59 meters @ 3.14 g/t Au in initial targets (see press release dated April 13, 2022).

Geological activities continue to reinforce the Company’s exploration pipeline, with good intersections at EPP at the connection of the pits on shale zone between Nosde and Lavrinhas, as well as confirmation of mineralization extension in Aranzazu and Matupa.

Finally, construction at the Company’s Almas Project is on schedule and the project is expected to be delivered on budget. The Company expects Almas to start production by April 2023. At the end of Q2 2022, about 47% of the project was completed and 90% of services and equipment budget had been already negotiated, mitigating risks of potential cost overruns, despite high inflation scenario.

Rodrigo Barbosa, the Company’s President and CEO, noted, “We are on track to meet the production guidance for the year. Despite some challenges in San Andres, Aura’s other two producing operations performed above expectations. Due to mine sequencing, we knew this quarter would be weaker, and we expect better production in Q3 and Q4. On geology, our exploration results during the quarter showed that we have important upsides on all our mines: Aranzazu Glory Hole is expected to continue down deep, and near mine exploration at EPP revealed a possible extension and connection between Nosde and Lavrinha with significant interceptions for 100 meters. At Matupa, drill holes at the Serrinhas target have shown over 200 meters of mineralization at MP2, where we announced the interception of 80 metres @ 3.89 g/t Au and 59 meters @ 3.14 g/t Au. Finally, construction at Almas is on schedule and on budget with 47% of the work completed.”