Unlock stock picks and a broker-level newsfeed that powers Wall Street.

Atalaya Mining PLC Announces Second Quarter 2021 Operations Update

In This Article:

NICOSIA, CYPRUS / ACCESSWIRE / July 13, 2021 /Atalaya Mining Plc (AIM:ATYM)(TSX:AYM) is pleased to announce its operations update for the second quarter of 2021 ("Q2 2021" or the "Period").

Proyecto Riotinto Operating Highlights

Q2

Q1

Full year

2021

2020

2021

2021 Guidance

Ore mined

(M tonnes)

3.3

3.2

3.3

15.1

Waste mined

(M tonnes)

8.0

5.7

7.4

25.9

Ore milled

(M tonnes)

4.0

3.6

4.0

15.0 - 15.5

Cu grade

(%)

0.42

0.44

0.41

0.42

Cu recovery

(%)

84.83

85.89

84.90

82 - 84

Cu production

(tonnes)

14,353

13,635

13,979

52,000 - 54,000

  • Copper production in Q2 2021 was 14,353 tonnes, 2.7 % higher than Q1 2021 and 5.3 % higher than Q2 2020.

  • The plant processed 4.03 million tonnes of ore during Q2 2021 equivalent to a throughput rate of approximately 16 Mtpa. Low grade stockpiles added extra tonnage.

  • The increase in copper production, when compared with the Company's guidance, is mainly attributable to higher throughput and, to a lesser extent, to better recoveries than planned.

  • Despite ongoing COVID-19 restrictions, mining operations have continued normally with higher production levels compared with previous quarters.

  • On-site copper concentrate inventories at the end of Q2 2021 were approximately 15,103 tonnes. All concentrate in stock at the beginning of the Period was delivered to the port at Huelva.

  • Copper prices increased during the Period compared with the previous quarter. Average spot prices increased from US$3.85/lb in Q1 2021 to US$4.40/lb in Q2 2021. The average realised price per pound of copper payable was $ 4.27 /lb compared with $ 3.62 /lb in the previous quarter. The realised price during Q2 2021 excluding QPs was approximately $ 4.40 /lb.

  • Cash operating costs for the Period are expected to be below full year 2021 cost guidance owing mainly to the Euro/U.S. dollar exchange rate of 1.2058 compared with 1.22 budgeted by the Company in its 2021 guidance, together with higher copper production and better recoveries. Further details on costs will be provided with the Q2 Financial Statements due to be reported in August.

Proyecto Riotinto Optimisation

  • During Q2 2021 some cost reduction initiatives were implemented such as the commissioning of a tailings thickener and changes to the lime circuit, both of which resulted in lower lime and energy consumption as well as a reduction in CO2 emissions.

  • Permitting of a 50 Mw solar plant for self-consumption advanced significantly and final construction permits are expected imminently.

  • New initiative focused on increased recoveries using different grinding media in the regrind mill.

Reserves and Resources Updates at Proyecto Riotinto

  • Following an independent reserve estimate which confirmed the status of a long life at the Cerro Colorado open pit, studies have advanced around the addition of further resources at Proyecto Riotinto.

  • A sizeable resource has been identified at San Dionisio deposit that is potentially mineable by open pit. Further polymetallic mineralization could be exploited using underground mining methods at the San Antonio and San Dionisio deposits.

  • Work has started on the preparation of an NI 43-101 compliant technical report which will be followed by PEA or PFS studies.