VANCOUVER, British Columbia, Nov. 21, 2024 (GLOBE NEWSWIRE) -- Aldebaran Resources Inc. (“Aldebaran” or the “Company”) (TSX-V: ALDE, OTCQX: ADBRF) is pleased to announce that field activities are underway and drilling has commenced at the Altar project in San Juan, Argentina. The Company has secured five drill rigs for the 2024/2025 field program, with an option on a sixth, and is targeting approximately 25,000 m of drilling.

Much of the information required to complete a Preliminary Economic Assessment (“PEA”) is already available except for results from the Phase 1 Nuton column leach testing, which is well underway. The 2024/2025 field program will focus primarily on collecting information required to complete a Pre-Feasibility Study (“PFS”) in H2-2026. The primary goals of the 2024/2025 field program are as follows:

  • Complete drilling for metallurgical samples required for Phase 2 Nuton sulphide leaching program (see Company news release dated November 7, 2024)

  • Complete infill drilling to upgrade resources from Inferred to Measured & Indicated where appropriate

  • Complete holes to collect geotechnical and hydrogeological data

  • Complete drilling into areas classified as waste due to lack of drilling (undefined waste)

Where possible, the Company will attempt to complete two or more of these goals with a single drill hole. The start of the season will be focused on delivering the metallurgical samples to Nuton, and thereafter will shift to the other stated goals.

John Black, Chief Executive Officer of Aldebaran, commented: “The last several years of work on the Altar project have focused on expanding the footprint of the deposit. Before the end of November, we will release an updated mineral resource estimate that will quantify a significant increase in the size of the Altar deposit since the last resource estimate in 2021. Work is underway on a PEA that we anticipate completing by the end of Q2-2025. The 2024/2025 field season will shift from resource expansion to more feasibility-level work. We will complete infill drilling where required, however, our focus this field season will be collecting data and preparing for a PFS that we anticipate will be completed towards the end of 2026. We feel that de-risking the project through PEA and PFS will add substantial value to an already impressive deposit.”

Qualified Person

The scientific and technical data contained in this news release has been reviewed and approved by Dr. Kevin B. Heather, B.Sc. (Hons), M.Sc, Ph.D, FAusIMM, FGS, Chief Geological Officer and director of Aldebaran, who serves as the qualified person (QP) under the definitions of National Instrument 43-101.