AbraSilver Provides Update on Diablillos Pre-Feasibility Study and La Coipita Exploration Program

In This Article:

TORONTO, Ontario - (NewMediaWire) - November 11, 2024 - AbraSilver Resource Corp. (TSX.V: ABRA; OTCQX: ABBRF) ("AbraSilver" or the "Company") is pleased to provide an update on the upcoming Pre-Feasibility Study ("PFS") for its wholly-owned Diablillos project in Argentina (the "Project"), and an exploration update on the La Coipita project.

Diablillos Pre-Feasibility Study Update

The Company continues to make significant progress on the updated Diablillos PFS, which remains on schedule to be finalized in early December 2024. The Company has engaged Mining Plus Peru S.A.C. as the lead consultant for the PFS, which will be prepared in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects.

The updated PFS aims to deliver a more robust evaluation of Diablillos, building upon the current Pre-Feasibility Study, which was published with an effective date of March 7, 2024. The updated PFS will provide a comprehensive update of the following key parameters:

  • Impact of the new investment regime for large investments (Rgimen de Incentivo Para Grandes Inversions, or RIGI), which significantly reduces the overall tax burden for the project. The impacts include:

  • An optimized mine plan that improves the overall sequencing of the open pit mine phases, bringing forward higher grade material from Octulto's shallow gold zone and improving the project cashflow;

  • Updated capital and operating cost estimates, including value engineering and de-risking initiatives to improve the overall Project;

  • Updated long term silver and gold prices to reflect recent market conditions.

John Miniotis, President and CEO, commented, "We are very pleased to be nearing completion of our updated PFS, which will provide significant enhancements and is expected to have a positive impact on the already robust economics of our Diablillos project. The updated study will also provide insights on the Feasibility Study, which is expected to be completed in Q4 2025, and will include the positive results from the current Phase 4 drill program and will serve as a strong foundation for continuing to progress Diablillos towards development. Alongside the advancements being made at La Coipita, we are very excited about the value and growth these projects bring to our shareholders."

La Coipita Project Exploration Update

Additionally, AbraSilver is pleased to provide an update on the La Coipita project which is under an option agreement with a subsidiary of Teck Resources Limited ("Teck"), as announced on January 22, 2024.